Plan Review Notes For Permit 18011185
Permit Number 18011185
Review Stop B
Sequence Number 1
Notes
Date Text
2018-02-03 12:01:52MOVING THE APPLICATION TO ENGINEERING'S MAILBOX. THE
 FOLLOWING ITEMS WILL NEED TO BE PASSED BEFORE ISSUANCE.
  
 1) PLUMBING PERMIT PULLED AND WHEN SEWER LATERAL
 CAPPED, A FINAL PLUMBING # 703 REQUESTED AND PASSED. A
 HYDRANT METER IS SUGGESTED TO KEEP THE DEMO WET AND
 RECEIVE THE PLUMBING FINAL QUICKER.
  
 2) ENGINEERING AND HISTORIC'S REVIEWS PASSED.
  
 3) THE REMAINING FEE BALANCE PAID.
  
 THANKS, TOM M. 561-805-6669