2018-01-29 05:42:10 | 01/29/2018 PLUMBING AND GAS 1ST REVIEW**DENIED** |
| |
| NOTE - A COMPREHENSIVE REVIEW COULD NOT BE DONE AT THIS |
| TIME AND ADDITIONAL PLAN REVIEW COMMENTS MAY BE |
| GENERATED UPON THE RE-REVIEW OF SUBMITTED CORRECTIONS. |
| |
| |
| 1) THE JOB COST MUST INCLUDE ALL LABOR AND MATERIAL TO |
| INCLUDE THE NEW EQUIPMENT. PROVIDE BONA-FIDE SIGNED |
| CONTRACT AND MATERIAL COST OF EQUIPMENT. FBC 109.3 |
| |
| 2) TYPE OF GAS (LP OR NATURAL). FBC 107.2. |
| |
| 3) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2014 |
| FBC-FUEL GAS CODE SEC.304.1, 614.5 (CLOTHES DRYERS) OR |
| 2014 FBC-RES. SEC. G 2407.1 AND G2439.4 (CLOTHES |
| DRYERS). SUBMIT COMBUSTION AIR CALCULATIONS FOR THE |
| ADDED GAS APPLIANCES. WHERE COMBUSTION AIR IS PROVIDED |
| BY THE BUILDING?S MECHANICAL VENTILATION SYSTEM, THE |
| SYSTEM SHALL PROVIDE THE SPECIFIED COMBUSTION AIR RATE |
| IN ADDITION TO THE REQUIRED VENTILATION AIR. FGC |
| SEC.304.9.3 OR FBCR G2407.9.3. |
| |
| |
| 4) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. |
| SEC. G2413.2. |
| |
| 5) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS / |
| INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY |
| COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND |
| FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014 |
| FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED |
| AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS |
| APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF |
| INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1 |
| |
| 6) SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE |
| LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION |
| AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN |
| RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER |
| HEATER SHALL COMPLY WITH THE MANUFACTURER'S |
| INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND |
| DRAWN. WPB AMEND. TO FBC SEC. 107.2.1 |
| |
| 7) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER IS |
| REPLACING AN EXISTING TANKLESS WATER HEATER OR IS IT |
| REPLACING A STORAGE TANK TYPE WATER HEATER OR IS IT |
| BEING ADDED TO THE EXISTING HOT WATER SYSTEM? INDICATE |
| ON THE APPLICATION IN THE DESCRIPTION OF WORK. FBC |
| 107.2.1 |
| |
| 8) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES |
| USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE |
| PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM |
| THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE |
| DESIGN OF THIS GAS SYSTEM. REFER TO THE 2014 FBC-FUEL |
| GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4 |
| (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2412.4, |
| G2412.8, G2413.1, G2413.2, & G2413.3. |
| |
| TIM HUNT |
| PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| 561-805-6695 |
| [email protected] |
| |