2018-02-05 16:34:40 | STORM WATER POLLUTION PREVENTION PLAN (SWPPP) |
| |
| 1. THE STORM WATER POLLUTION PREVENTION PLAN (SWPPP) IS |
| COMPRISED OF AN EROSION AND SEDIMENTATION CONTROL PLAN, |
| THE EROSION AND SEDIMENTATION CONTROL DETAILS, AND ALL |
| SUBSEQUENT REPORTS AND RELATED DOCUMENTS PROVIDED AND |
| UPDATED BY THE CONTRACTOR. |
| |
| 2. ALL CONTRACTORS AND SUBCONTRACTORS INVOLVED WITH |
| STORM WATER POLLUTION REVENTION SHALL OBTAIN A COPY OF |
| THE SWPPP AND THE STATE OF FLORIDA NATIONAL POLLUTANT |
| DISCHARGE ELIMINATION SYSTEM GENERAL PERMIT (NPDES |
| PERMIT) AND BECOME FAMILIAR WITH THEIR CONTENTS. |
| |
| 3. THE CONTRACTOR SHALL IMPLEMENT BEST MANAGEMENT |
| PRACTICES (BMP'S) AS REQUIRED BY THE SWPPP. ADDITIONAL |
| BEST MANAGEMENT PRACTICES SHALL BE IMPLEMENTED AS |
| DICTATED BY CONDITIONS AT NO ADDITIONAL COST TO THE |
| OWNER THROUGHOUT ALL PHASES OF CONSTRUCTION. |
| |
| 4. BEST MANAGEMENT PRACTICES AND CONTROLS SHALL CONFORM |
| TO FEDERAL, STATE, OR LOCAL REQUIREMENTS OR MANUAL OF |
| PRACTICE, AS APPLICABLE. THE CONTRACTOR SHALL IMPLEMENT |
| ADDITIONAL CONTROLS AS DIRECTED BY THE PERMITTING |
| AGENCY OR THE OWNER. |
| |
| 5. EROSION CONTROL PLAN MUST CLEARLY DELINEATE ALL |
| STATE WATERS. PERMITS FOR ANY CONSTRUCTION ACTIVITY |
| IMPACTING STATE WATERS OR REGULATED WETLANDS MUST BE |
| MAINTAINED ON SITE AT ALL TIMES. |
| |
| 6. THE CONTRACTOR SHALL MINIMIZE CLEARING TO THE |
| MAXIMUM EXTENT PRACTICAL OR AS REQUIRED BY THE GENERAL |
| PERMIT, IF ONE HAS BEEN ISSUED. |
| |
| 7. CONTRACTOR SHALL DENOTE ON PLAN THE TEMPORARY |
| PARKING AND STORAGE AREA WHICH SHALL ALSO BE USED AS |
| THE EQUIPMENT MAINTENANCE AND CLEANING AREA, EMPLOYEE |
| PARKING AREA, AND AREA FOR LOCATING PORTABLE |
| FACILITIES, OFFICE TRAILERS, AND TOILET FACILITIES. |
| |
| 8. ALL WASH WATER (CONCRETE TRUCKS, VEHICLE CLEANING, |
| EQUIPMENT CLEANING, ETC.) SHALL BE DETAINED AND |
| PROPERLY TREATED OR DISPOSED. |
| |
| 9. SUFFICIENT OIL AND GREASE ABSORBING MATERIALS AND |
| FLOTATION BOOMS SHALL BE MAINTAINED ON SITE OR READILY |
| AVAILABLE TO CONTAIN AND CLEAN-UP FUEL OR CHEMICAL |
| SPILLS AND LEAKS. |
| |
| 10. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE CONTROL |
| OF DUST AND DIRT RISING AND SCATTERING IN THE AIR |
| DURING CONSTRUCTION AND SHALL PROVIDE WATER SPRINKLING |
| OR OTHER SUITABLE METHODS OF CONTROL. THE USE OF MOTOR |
| OILS AND OTHER PETROLEUM BASED OR TOXIC LIQUIDS FOR |
| DUST SUPPRESSION OPERATIONS IS PROHIBITED. THE |
| CONTRACTOR SHALL COMPLY WITH ALL GOVERNING REGULATIONS |
| PERTAINING TO ENVIRONMENTAL PROTECTION. |
| |
| 11. RUBBISH, TRASH, GARBAGE, LITTER, OR OTHER SUCH |
| MATERIALS SHALL BE DEPOSITED INTO SEALED CONTAINERS. |
| MATERIALS SHALL BE PREVENTED FROM LEAVING THE PREMISES |
| THROUGH THE ACTION OF WIND OR STORM WATER DISCHARGE |
| INTO DRAINAGE DITCHES OR WATERS OF THE STATE. |
| |
| 12. ALL STORM WATER POLLUTION PREVENTION MEASURES |
| PRESENTED ON THE PLAN, SHALL BE INITIATED AS SOON AS |
| PRACTICABLE. |
| |
| 13. THE CONTRACTOR SHALL INSTALL INLET PROTECTION ON |
| ALL EXISTING AND PROPOSED DRAINAGE STRUCTURES FOR THE |
| DURATION OF CONSTRUCTION AND UNTIL ACCEPTANCE OF THE |
| PROJECT BY THE OWNER. ALL DRAINAGE STRUCTURES AND PIPES |
| WITHIN THE LIMITS OF CONSTRUCTION SHALL BE CLEANED OF |
| DEBRIS AS REQUIRED DURING AND AT THE END OF |
| CONSTRUCTION TO PROVIDE POSITIVE DRAINAGE FLOWS. |
| |
| 14. STABILIZATION PRACTICES SHOULD BE INITIATED AS SOON |
| AS PRACTICAL. |
| |
| 15. DISTURBED PORTIONS OF THE SITE WHERE CONSTRUCTION |
| ACTIVITY HAS PERMANENTLY STOPPED SHALL BE PERMANENTLY |
| STABILIZED. THESE AREAS SHALL BE STABILIZED NO LATER |
| THAN 7 DAYS AFTER THE LAST CONSTRUCTION ACTIVITY |
| OCCURRED. |
| |
| 16. IF A GRAVEL CONSTRUCTION ENTRANCE IS NOT USED OR |
| THE ACTION OF VEHICLES TRAVELING OVER THE GRAVEL |
| CONSTRUCTION ENTRANCE IS NOT SUFFICIENT TO REMOVE THE |
| MAJORITY OF DIRT OR MUD, THEN THE TIRES MUST BE WASHED |
| BEFORE THE VEHICLES ENTER A PUBLIC ROAD. IF WASHING IS |
| USED, PROVISIONS MUST BE MADE TO INTERCEPT THE WASH |
| WATER AND TRAP THE SEDIMENT BEFORE IT IS CARRIED OFF |
| THE SITE. |
| |
| 17. ALL MATERIALS SPILLED, DROPPED, WASHED, OR TRACKED |
| FROM VEHICLES ONTO ROADWAYS OR INTO STORM DRAINS MUST |
| BE REMOVED AS SOON AS POSSIBLE. |
| |
| 18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REMOVING |
| ANY SEDIMENT THAT MAY HAVE COLLECTED IN THE STORM SEWER |
| DRAINAGE SYSTEMS IN CONJUNCTION WITH THE DEMOLITION, |
| CONSTRUCTION, OR STABILIZATION OF THE SITE. |
| |
| 19. ON-SITE & OFF-SITE SOIL STOCKPILE AND BORROW AREAS |
| SHALL BE PROTECTED FROM EROSION AND SEDIMENTATION |
| THROUGH IMPLEMENTATION OF BEST MANAGEMENT PRACTICES. |
| STOCKPILE AND BORROW AREA LOCATIONS SHALL BE NOTED ON |
| THE EROSION CONTROL PLAN AND PERMITTED IN ACCORDANCE |
| WITH GENERAL PERMIT REQUIREMENTS. |
| |
| 20. SLOPES SHALL BE LEFT IN A ROUGHENED CONDITION |
| DURING THE GRADING PHASE TO REDUCE RUNOFF VELOCITIES |
| AND EROSION. |
| |
| 21. DUE TO GRADE CHANGES DURING THE DEVELOPMENT OF THE |
| PROJECT, THE CONTRACTOR SHALL BE RESPONSIBLE FOR |
| ADJUSTING THE EROSION CONTROL MEASURES (SILT FENCES, |
| ETC.) TO PREVENT EROSION. |
| |
| 22. ALL CONSTRUCTION SHALL BE STABILIZED AT THE END OF |
| EACH WORKING DAY, THIS INCLUDES BACK FILLING OF |
| TRENCHES FOR UTILITY DEMOLITION OR CONSTRUCTION AND |
| PLACEMENT OF GRAVEL OR BITUMINOUS PAVING FOR ROAD |
| CONSTRUCTION. |
| |
| 23. EROSION AND SEDIMENTATION CONTROL PLANS PROVIDED |
| HEREIN ARE A GUIDELINE ONLY. THE CONTRACTOR IS |
| RESPONSIBLE FOR PREPARING THE FINAL POLLUTION |
| PREVENTION PLAN. THE PLAN SHALL BE SUBMITTED TO THE |
| OWNER WHICH DEMONSTRATES THE MECHANISMS AND PRACTICES |
| THAT WILL BE EMPLOYED TO PROTECT THE CONSTRUCTION SITE |
| AND SURROUNDING AREA DURING CONSTRUCTION. THE PLAN |
| SHALL BE CONSISTENT WITH FEDERAL NATIONAL POLLUTANT |
| DISCHARGE ELIMINATION SYSTEM (NPDES PERMIT REQUIREMENTS |
| PERTAINING TO POLLUTION PREVENTION PLANS. THE PLAN |
| SHALL INCLUDE, BUT NOT BE LIMITED TO, THE LOCATIONS OF |
| SILT BARRIERS, EMERGENCY RESPONSE PRACTICES, AND OTHER |
| METHODS TO PREVENT POLLUTION. REFUELING OR STORAGE OF |
| VEHICLES OR EQUIPMENT THAT UTILIZE PETROLEUM BASED |
| PRODUCTS SHALL BE PROHIBITED ANYWHERE WITHIN 50 FEET OF |
| A WATER'S EDGE. THE PLAN SHALL BE FILED WITH ALL |
| APPLICABLE REGULATORY AGENCIES BY THE CONTRACTOR. REFER |
| TO FURTHER NOTES AND DETAILS WITHIN THESE DOCUMENTS. |
| |
| 24. SILT FENCE IS REQUIRED AS SHOWN ON THE PLANS AND |
| ANYWHERE ADDITIONAL AT THE CONTRACTOR'S DISCRETION. |
| SILT FENCE IS NOT APPLICABLE IN PAVEMENT AREAS. LIMITS |
| OF CONSTRUCTION SHOWN ARE DIAGRAMATIC. CONTRACTOR TO |
| PROVIDE PLAN FOR SHOP DRAWING REVIEW. |
| |
| DEMOLITION NOTES |
| |
| 1. BROKEN PAVEMENT OR OTHER DEBRIS SHALL BE REMOVED |
| FROM THE SITE AS SOON AS PRACTICAL. EXCAVATED MATERIALS |
| SHALL NOT BE STOCKPILED IN THE RIGHT-OF-WAY OR EASEMENT |
| DURING CONSTRUCTION. |
| |
| 2. VEGETATION, MUCK, AND ANY DELETERIOUS MATERIAL |
| WITHIN THE RIGHT-OF-WAY LIMITS OF ALL STREETS MUST BE |
| REMOVED AND REPLACED WITH CLEAN FILL MATERIAL, FREE OF |
| STUMPS, LARGE ROOTS, OR OTHER MATTER NOT SUITABLE FOR |
| INCLUSION IN ROADWAY FILL. |
| |
| 3. AFTER REMOVAL OF UNDERGROUND PIPES, THE TRENCHES |
| SHALL BE BACKFILLED. BACKFILL MATERIAL SHALL BE PLACED |
| IN LAYERS NOT TO EXCEED TWELVE (12) INCHES IN |
| THICKNESS, WITH EACH LAYER CAREFULLY COMPACTED TO |
| NINETY-EIGHT PERCENT (98%) OF MAXIMUM DENSITY, PER |
| AASTHO T-180 AND TESTED, BEFORE PLACING SUCCEEDING |
| LAYERS. DENSITY TESTS SHALL BE TAKEN AT MAXIMUM |
| TWO-HUNDRED FOOT (200') INTERVALS, STAGGERED EACH SIDE |
| OF THE TRENCH. AT A MINIMUM, BACKFILLING AND COMPACTION |
| SHALL BE PER FDOT, CITY OF WEST PALM BEACH, AND/OR |
| AASHTO STANDARDS. |
| |
| 4. CONTRACTOR SHALL STORE AND PROTECT ANY ITEMS NOTED |
| TO BE RELOCATED. ANY DAMAGED ITEMS SHALL BE REPLACED AT |
| THE EXPENSE OF THE CONTRACTOR. |
| |
| 5. THE OWNER MAY DESIGNATE ADDITIONAL ITEMS TO BE |
| SALVAGED AND PROVIDED TO THE OWNER. |
| |
| 6. REFER TO THE DEMOLITION PLAN FOR ADDITIONAL DETAILS |
| OF EXISTING STRUCTURES, ETC., LOCATED WITHIN THE |
| PROJECT SITE. UNLESS OTHERWISE NOTED, ALL EXISTING |
| BUILDINGS, STRUCTURES, SLABS, CONCRETE, ASPHALT, DEBRIS |
| PILES, SIGNS, AND ALL APPURTENANCES ARE TO BE REMOVED |
| FROM THE SITE BY THE CONTRACTOR AND PROPERLY DISPOSED |
| OF IN A LEGAL MANNER. |
| |
| 7. THE CONTRACTOR SHALL REFER TO THE DEMOLITION PLAN |
| FOR DEMOLITION/PRESERVATION OF EXISTING TREES. ALL |
| TREES NOT SPECIFICALLY SHOWN TO BE REMOVED OR RELOCATED |
| SHALL BE PRESERVED . TREE PROTECTION FENCING SHALL BE |
| INSTALLED PRIOR TO ANY DEMOLITION. ALL TRESS TO BE |
| SAVED UNLESS OTHERWISE NOTED. |
| |
| 8. CONTRACTOR TO NOTE EXISTING TREES TO REMAIN. SHOULD |
| ANY TREE TO BE REMAIN BE DAMAGED BY THE CONTRACTOR, IT |
| WILL REQUIRE REPLACEMENT IN KIND. |
| |
| MAINTENANCE |
| |
| 1. ALL MEASURES STATED ON THE EROSION AND SEDIMENTATION |
| CONTROL PLAN, AND IN THE STORM WATER POLLUTION |
| PREVENTION PLAN, SHALL BE MAINTAINED IN FULLY |
| FUNCTIONAL CONDITION UNTIL NO LONGER REQUIRED FOR A |
| COMPLETED PHASE OF WORK OR FINAL STABILIZATION OF THE |
| SITE. ALL EROSION AND SEDIMENTATION CONTROL MEASURES |
| SHALL BE CHECKED BY A QUALIFIED PERSON AT LEAST ONCE |
| EVERY SEVEN CALENDAR DAYS AND WITHIN 24 HOURS OF THE |
| END OF A 0.5 INCH RAINFALL EVENT, AND CLEANED AND |
| REPAIRED IN ACCORDANCE WITH THE FOLLOWING: |
| |
| 2. INLET PROTECTION DEVICES AND BARRIERS SHALL BE |
| REPAIRED OR REPLACED IF THEY SHOW SIGNS OF UNDERMINING, |
| OR DETERIORATION. |
| |
| 3. ALL SEEDED AREAS SHALL BE CHECKED REGULARLY TO SEE |
| THAT A GOOD STAND IS MAINTAINED. AREAS SHOULD BE |
| FERTILIZED, WATERED AND RESEEDED AS NEEDED. |
| |
| 4. SILT FENCES SHALL BE REPAIRED TO THEIR ORIGINAL |
| CONDITIONS IF DAMAGED. SEDIMENT SHALL BE REMOVED FROM |
| THE SILT FENCES WHEN IT REACHES ONE-HALF THE HEIGHT OF |
| THE SILT FENCE. |
| |
| 5. THE CONSTRUCTION ENTRANCE SHALL BE MAINTAINED IN A |
| CONDITION WHICH WILL PREVENT TRACKING OR FLOW OF MUD |
| ONTO PUBLIC RIGHTS-OF-WAY. THIS MAY REQUIRE PERIODIC |
| TOP DRESSING OF THE CONSTRUCTION ENTRANCE AS CONDITIONS |
| DEMAND. |
| |
| 6. THE TEMPORARY PARKING AND STORAGE AREA SHALL BE KEPT |
| IN GOOD CONDITION (SUITABLE FOR PARKING AND STORAGE). |
| THIS MAY REQUIRE PERIODIC TOP DRESSING OF THE TEMPORARY |
| PARKING AS CONDITIONS DEMAND. |
| |
| 7. ALL CONSTRUCTION SHALL BE DONE IN A SAFE MANNER, |
| SPECIFICALLY, THE RULES AND REGULATIONS OF THE |
| OCCUPATIONAL SAFETY AND HEALTH ADMINISTRATION (OSHA), |
| THE FLORIDA DEPARTMENT OF TRANSPORTATION (FDOT), THE |
| MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (MUTCD), |
| SHALL BE STRICTLY OBSERVED. |
| |
| 8. CONTRACTOR SHALL BE SOLELY RESPONSIBLE FOR |
| COMPLIANCE WITH THE STATE OF FLORIDA TRENCH SAFETY ACT. |
| HTTP://DEP.STATE.FL.US/WATER/STORMWATER/INDEX.HTM |
| HTTP://DEP.STATE.FL.US/WATER/STORMWATER/NPDES/SWPPP.HTM |
| |
| SOFIA QUINONES-BENEJAM, EI |
| PROJECT ENGINEER |
| CITY OF WEST PALM BEACH |
| 401 CLEMATIS STREET, 4TH FLOOR |
| WEST PALM BEACH, FL 33402 |
| (MAILING ADDRESS: PO BOX 3366) |
| P: 561.494.1108 |
| C: 561.459.6518 |
| F: 561.494.1116 |
| EMAIL: [email protected] |
| |