Plan Review Notes
Plan Review Notes For Permit 17111142
Permit Number 17111142
Review Stop B
Sequence Number 5
Notes
Date Text
2018-11-14 09:21:14PLAN
 REVIEW COMMENTS
 3611 S. FLAGLER DRIVE
 "THE CRYSTAL" 6 UNIT, 7 STOREY R-2 (CONDO)
 AE FLOOD ZONE
  
 5TH REVIEW: FBC FIFTH EDITION (2014)
 ROBERT MCDOUGAL, CBO
 COMMERCIAL COMBINATION PLANS EXAMINER
 (561) 805-6714
 [email protected]
  
 DENIED BY BUILDING
 PLEASE ADDRESS THE ITEMS NOTED BELOW:
  
 1) NOT ADDRESSED. NEW COMMENTS: THRESHOLD BUILDINGS
 REQUIRE THREE SETS OF CONSTRUCTION DOCUMENTS. ONLY TWO
 SETS OF THE PILE SURVEYS WERE SUBMITTED. THE LETTER
 FROM THE ENGINEER, RONALD M. JEZERINAC P.E., STATES
 THAT THE PILE SURVEYS THAT THEY REVIEWED HAVE HIS SHOP
 DRAWING APPROVAL STAMP. THE ONES THAT WERE SUBMITTED DO
 NOT HAVE SHOP DRAWING REVIEW STAMPS ON THEM.
 -FBC 107.2.1.3 PROVIDE CERTIFICATION DOCUMENTS FROM THE
 THRESHOLD INSPECTOR THAT HAVE BEEN REVIEWED AND
 ACCEPTED BY THE DESIGNER OF RECORD ATTESTING THAT THE
 PRODUCTION PILES AND PILE CAPS HAVE BEEN INSPECTED AND
 ARE INSTALLED PER THE PLANS FROM THE DESIGNER OF
 RECORD.
  
 2) NOT ADDRESSED. NEW COMMENT: THE (3) THRESHOLD
 INPECTION PLANS THAT WERE SUBMITTED HAVE DIGITAL
 SIGNATURES, WHICH ARE ONLY ACCEPTABLE FOR
 ELECTRONICALLY SUBMITTED DOCUMENTS.
 -FBC 110.3.7 SUBMIT THREE SETS OF A THRESHOLD
 INSPECTION PLAN FROM THE NEW DESIGNER OF RECORD. THE
 ENGINEER'S ORIGINAL HANDWRITTEN SIGNATURES ARE REQUIRED
 ON PAPER DOCUMENTS PER FAC 61G15-23.003
  
 3) NOT ADDRESSED. NEW COMMENT: I DID NOT SEE TERMITE
 PROTECTION SPECIFIED ON THE PLANS.
 -SHOW COMPLIANCE WITH FBC1816.1 TERMITE PROTECTION.
  
 4) ADDRESSED. I REDLINED SHEET A101 TO REFER TO REVISED
 SHEETS A101 AND S3.1.
 -FBC 107.2.1THERE ARE SOME DISCREPANCIES BETWEEN THE
 ARCHITECTURAL PLANS AND THE STRUCTURAL PLANS THAT NEED
 TO BE ADDRESSED. ON SHEET S3.1 THE OPENING AND STAIRS
 ARE SHOWN ON THE WEST SIDE OF THE FIRE PUMP ROOM. THE
 SITE PLANS AND SHEETS A101 AND A201 SHOW THE DOOR ON
 THE SOUTH END OF THE FIRE PUMP ROOM.
  
 5) NEW COMMENTS: THRESHOLD BUILDINGS REQUIRE THREE (3)
 SETS OF CONSTRUCTION DOCUMENTS TO BE SUBMITTED FOR
 REVIEW. ONLY TWO SETS OF THE GEOTECHNICAL REPORT, THE
 SITE-SPECIFIC FLOOD ZONE ANALYSIS THE LETTERS FROM
 NUTTING ENGINEERS AND JEZERINAC GROUP WERE SUBMITTED.
 FBC 107.1
  
 6) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT A
 RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW
 COMMENTS HAS BEEN ADDRESSED.
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved