Date |
Text |
2018-11-14 09:21:14 | PLAN |
| REVIEW COMMENTS |
| 3611 S. FLAGLER DRIVE |
| "THE CRYSTAL" 6 UNIT, 7 STOREY R-2 (CONDO) |
| AE FLOOD ZONE |
| |
| 5TH REVIEW: FBC FIFTH EDITION (2014) |
| ROBERT MCDOUGAL, CBO |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| (561) 805-6714 |
| [email protected] |
| |
| DENIED BY BUILDING |
| PLEASE ADDRESS THE ITEMS NOTED BELOW: |
| |
| 1) NOT ADDRESSED. NEW COMMENTS: THRESHOLD BUILDINGS |
| REQUIRE THREE SETS OF CONSTRUCTION DOCUMENTS. ONLY TWO |
| SETS OF THE PILE SURVEYS WERE SUBMITTED. THE LETTER |
| FROM THE ENGINEER, RONALD M. JEZERINAC P.E., STATES |
| THAT THE PILE SURVEYS THAT THEY REVIEWED HAVE HIS SHOP |
| DRAWING APPROVAL STAMP. THE ONES THAT WERE SUBMITTED DO |
| NOT HAVE SHOP DRAWING REVIEW STAMPS ON THEM. |
| -FBC 107.2.1.3 PROVIDE CERTIFICATION DOCUMENTS FROM THE |
| THRESHOLD INSPECTOR THAT HAVE BEEN REVIEWED AND |
| ACCEPTED BY THE DESIGNER OF RECORD ATTESTING THAT THE |
| PRODUCTION PILES AND PILE CAPS HAVE BEEN INSPECTED AND |
| ARE INSTALLED PER THE PLANS FROM THE DESIGNER OF |
| RECORD. |
| |
| 2) NOT ADDRESSED. NEW COMMENT: THE (3) THRESHOLD |
| INPECTION PLANS THAT WERE SUBMITTED HAVE DIGITAL |
| SIGNATURES, WHICH ARE ONLY ACCEPTABLE FOR |
| ELECTRONICALLY SUBMITTED DOCUMENTS. |
| -FBC 110.3.7 SUBMIT THREE SETS OF A THRESHOLD |
| INSPECTION PLAN FROM THE NEW DESIGNER OF RECORD. THE |
| ENGINEER'S ORIGINAL HANDWRITTEN SIGNATURES ARE REQUIRED |
| ON PAPER DOCUMENTS PER FAC 61G15-23.003 |
| |
| 3) NOT ADDRESSED. NEW COMMENT: I DID NOT SEE TERMITE |
| PROTECTION SPECIFIED ON THE PLANS. |
| -SHOW COMPLIANCE WITH FBC1816.1 TERMITE PROTECTION. |
| |
| 4) ADDRESSED. I REDLINED SHEET A101 TO REFER TO REVISED |
| SHEETS A101 AND S3.1. |
| -FBC 107.2.1THERE ARE SOME DISCREPANCIES BETWEEN THE |
| ARCHITECTURAL PLANS AND THE STRUCTURAL PLANS THAT NEED |
| TO BE ADDRESSED. ON SHEET S3.1 THE OPENING AND STAIRS |
| ARE SHOWN ON THE WEST SIDE OF THE FIRE PUMP ROOM. THE |
| SITE PLANS AND SHEETS A101 AND A201 SHOW THE DOOR ON |
| THE SOUTH END OF THE FIRE PUMP ROOM. |
| |
| 5) NEW COMMENTS: THRESHOLD BUILDINGS REQUIRE THREE (3) |
| SETS OF CONSTRUCTION DOCUMENTS TO BE SUBMITTED FOR |
| REVIEW. ONLY TWO SETS OF THE GEOTECHNICAL REPORT, THE |
| SITE-SPECIFIC FLOOD ZONE ANALYSIS THE LETTERS FROM |
| NUTTING ENGINEERS AND JEZERINAC GROUP WERE SUBMITTED. |
| FBC 107.1 |
| |
| 6) IN ORDER TO REDUCE PLAN REVIEW TIME, PLEASE SUBMIT A |
| RESPONSE LETTER INDICATING HOW EACH OF THE REVIEW |
| COMMENTS HAS BEEN ADDRESSED. |
| |
| |
| |