2017-12-05 07:33:34 | GOOD MORNING, |
| NO UTILITY RELEASES WERE INCLUDED IN THIS APPLICATION. |
| I WILL NEED COPIES OF THE FOLLOWING BEFORE I CAN ISSUE |
| THE DEMO PERMIT; |
| |
| 1) CONFIRMATION FROM F.P.L. THAT THE POWER HAS BEEN |
| DISCONNECTED. |
| |
| 2) CONFIRMATION FROM F.P.U. THAT THE GAS HAS BEEN |
| DISCONNECTED. |
| |
| 3) CONFIRMATION FROM OUR WATER DEPARTMENT THAT A |
| REQUEST WAS RECEIVED TO PULL THE WATER METER. NOW IS |
| WHEN ARRANGEMENTS CAN BE MADE TO KEEP THE DEMO WET. A |
| HYDRANT METER CAN BE PAID FOR OR IF A OTHER |
| ARRANGEMENTS SUCH AS A HOSE BIB AND BACKFLOW.WHEN THE |
| WATER DEPARTMENT IS ON SITE, THEY WILL THEN MARK THE |
| SEWER LATERAL LOCATION WITH GREEN PAINT. |
| |
| 4) A TURN-A-ROUND PLUMBING PERMIT WILL NEED TO BE |
| PULLED TO CAP THE SEWER LATERAL. WHEN COMPLETED, A |
| FINAL PLUMBING INSPECTION #703 SHOULD BE REQUESTED TO |
| FINAL THAT PERMIT OUT. THIS SHOULD BE DONE PRIOR TO |
| ISSUANCE OF THE DEMO PERMIT. |
| |
| 5) A RODENT LETTER WILL NEED TO BE INCLUDED. THIS IS |
| PREPARED BY YOUR PEST CONTROL COMPANY AFTER VISITING |
| THE SITE AND TREATING FOR RODENTS IF FOUND. A |
| CONFIRMATION LETTER BY THEM WILL THEN NEED TO BE |
| INCLUDED. |
| |
| 6) A DEBRIS DISPOSAL FORM WILL NEED TO BE FILLED OUT. |
| THIS CAN BE DONE AT PERMIT PICKUP. |
| |
| 7) A COPY OF THE N.O.C. SHOULD BE INCLUDED IN THE |
| RELEASE PACKAGE. |
| |
| 8) IF THE BUILDING IS COMMERCIAL, THEN AN ASBESTOS |
| SURVEY WILL NEED TO BE COMPLETED AND A COPY PROVIDED. |
| |
| 9) HISTORIC AND ENGINEERING DEPARTMENT SIGN OFF. I WILL |
| ROUTE YOUR APPLICATION TO ENGINEERING NEXT. |
| |
| IF ANY QUESTIONS, I CAN BE REACHED AT 561-805-6669 |
| |
| THANKS, TOM |