Plan Review Notes
Plan Review Notes For Permit 17110117
Permit Number 17110117
Review Stop P
Sequence Number 3
Notes
Date Text
2018-05-12 05:25:231) THERE ARE TWO SETS OF PLANS THAT ARE MISSING THE
 "CVR" SHEET AND ALSO THE ELECTRICAL PLANS. SUBMIT TWO
 COMPLETE SETS OF PLANS FOR REVIEW. WPB AMEND TO FBC
 SEC. 107.1.
 2) ONE SET OF PLANS CONTAINS MEP SHEETS THAT ARE NOT
 SIGNED AND SEALED BY THE DESIGN PROFESSIONAL. COMPLY
 WITH FL. ADMIN. CODE RULE 61G15-23.001.
 3) SHT. A1.0 - DETAIL #3 - ENLARGED PLAN - THE
 ELEVATION ARROWS LISTING THE ELEVATION DETAIL DO NOT
 CORRELATE WITH THE ELEVATIONS ON THE PLANS AND ALSO
 REFER TO SHT. A4 WHICH THERE IS NO SUCH SHEET. REVISE.
 WPB AMEND. TO FBC SEC. 107.2.1.
 4) SHT. A1.0 - THE OUTLET OF THE TOILET PAPER DISPENSER
 IN THE HANDICAPPED TOILET ROOMS SHALL BE LOCATED A
 MINIMUM OF 15 INCHES AND A MAXIMUM OF 48 INCHES ABOVE
 THE FINISH FLOOR. 2017 FBC-ACCESS. SEC.604.7. SHOW THIS
 ON SHT. A1.0.
 5) SHOW THE REQUIRED TURNING SPACE IN RESTROOM #105 IN
 ACCORDANCE WITH THE 2017 FBC-ACCESS. SEC.304.1,
 304.3.1, 304.3.2.
 6) SHT. A1.0 - RESTROOM #105 - SHOW THE WIDTH DIMENSION
 BETWEEN THE CORNER EDGE OF THE LAVATORY AND THE END OF
 THE URINAL PARTITION.COMPLY WITH 2017 FBC-ACCESS.
 SEC.305.3.
 7) SUBMIT 2 COMPLETE COPIES OF THE MANUFACTURER'S
 INSTALLATION MANUAL FOR THE DISHWASHER. WPB AMEND. TO
 FBC SEC. 107.2.1. 2ND REQUEST.
 8) SHT. P-2 - INDICATE ON THE EXPANSION TANK SIZING
 CHART ON SHT. P-2 THE SIZE OF THE EXPANSION TANK TO BE
 INSTALLED ON THE WATER SUPPLY SYSTEM.
 9) SUBMIT TWO COPIES OF THE INSTALLATION MANUAL FOR THE
 WATER FILTRATION SYSTEM. WPB AMEND. TO FBC SEC.
 107.2.1. 2ND REQUEST.
 10) SHT. A1.0 - DETAIL #4 - THE LOCATION OF THE SIDE
 GRAB BAR SHALL COMPLY WITH 2017 FBC-ACCESS.
 SEC.604.5.1. THE GRAB BAR SHALL EXTEND A MINIMUM OF 54
 INCHES FROM THE REAR WALL. REFER TO 2017 FBC-ACCESS.
 FIGURE 604.5.1.3RD REQUEST.
 11) SHT. P-2 - THE DISCHARGE LIINE FROM THE WORK TABLE
 IN BOH #103 SHALL BE INDIRECTLY WASTED TO THE GREASY
 WASTE SYSTEM PER THE 2017 FBC-PLUMBING SEC.802.2.
 12) SUBMIT AN EXPANDED PIPNG DETAIL / DIAGRAM FOR THE
 HOT WATER RECIRCULATION SYSTEM. THE HOT WATER OR
 TEMPERED WATER RETURN LINE SHALL BE INSTALLED IN
 ACCORDANCE WITH THE 2017 FBC-PLUMBING SEC.607.2.2. A
 NOTE HAS BEEN PLACED ON THE PLAN TO THIS EFFECT BUT IS
 INADEQUATE. I HAVE INCLUDED A DIAGRAM AND TEXT FROM THE
 PLUMBING CODE COMMENTARY IN THE PLAN REVIEW FOLDER FOR
 A REFERENCE.2ND REQUEST.
 13) NOTE: ALL PLUMBING PIPES SHALL BE EXPOSED AND
 TESTED FOR INSPECTION OR A VIDEO OF SANITARY PIPING
 SHALL BE APPROVED BY TIM LARGE FOR THE ROUGH
 INSPECTIONS PER FBC PL 312. ROUGH INSPECTION WILL NOT
 PASS IF THE VIDEO SSHOWS ANY PORTION OF THE UNDERGROUND
 PIPING EXHIBITING NON-COMPLIANCE WITH THE PLUMBING CODE
 AND IN THAT INSTANCE THE UNDERSLAB PIPING SHALL BE
 EXPOSED FOR AND CORRECTED AND INSPECTED FOR COMPLIANCE.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  