Date |
Text |
2017-11-28 13:57:20 | 11/28/2017 GAS 3RD REVIEW **DENIED** |
| |
| |
| COMMENTS FROM LAST REVIEW HAVE NOT BEEN ADDRESSED. IT |
| IS RECOMMENED YOU CONTRACT THIS PLAN REVIEWER. A 4TH |
| DENIED PLAN REVIEW WILL RESULT IN A 4XFEE FOR PLAN |
| REVIEW |
| |
| |
| 1) A PROPER GAS ISOMETRIC RISER DIAGRAM SHOWING THE TIE |
| IN SIZE TO THE EXISTING SYSTEM WITH THE CONNECTION TO |
| THE GAS VALVE, REGULATOR AND DRIP LEG AT THE GENERATOR. |
| FBC 107.3.5.THE PLANS INDICATE AN EXISTING GAS METER. |
| THE BTU LOAD OF THE EXISTING GAS SYSTEM MUST BE ADDED |
| INTO THE TOTAL BTU LOAD ON THE SYSTEM TO ENSURE THE |
| EXISTING SYSTEM IS PROPERLY SIZED. IF UNDERSIZED, THE |
| EXISTING SYSTEM MUST BE REDONE TO ENSURE A SAFE |
| OPERATING SYSTEM. SUBMIT A GAS PIPING RISER DIAGRAM |
| THAT SHOWS THE TYPE OF EXISTING APPLIANCE, THE BTU LOAD |
| OF EACH APPLIANCE, THE PIPE SIZE AND TYPE OF PIPE TO |
| EACH APPLIANCE, AND THE DISTANCE OF THE LONGEST LENGTH |
| OF PIPING FROM THE POINT OF DELIVERY TO THE MOST REMOTE |
| OUTLET AND THE LOAD OF THE SECTION |
| |
| 2) YOUR SIZING TABLE IS THE INCORRECT CHART. IT SHOULD |
| BE SCH 40 METALLIC PIPING AT .5 LBS FGC 402.3. SUBMIT |
| TWO COPIES OF THE APPLICABLE SIZING TABLES USED TO SIZE |
| THE GAS SYSTEM OR PLACE A NOTE ON THE PLANS/DRAWINGS |
| SPECIFYING WHICH SIZING TABLE(S) FROM THE GAS CODE OR |
| OTHER STANDARD THAT WERE USED IN THE DESIGN OF THIS GAS |
| SYSTEM. REFER TO THE 2014 FBC-FUEL GAS SECS. 401.4, |
| 401.8 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4 (37) |
| OR 2014 FBC-RES. SEC. G2412.4, G2412.8, G2413.1, |
| G2413.2, & G2413.3 |
| |
| |
| TIM HUNT |
| PLUMBING INSPECTOR / PLUMBING PLAN REVIEWER |
| CITY OF WEST PALM BEACH DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| 561-805-6695 |
| [email protected] |
| |