Plan Review Notes
Plan Review Notes For Permit 17090199
Permit Number 17090199
Review Stop E
Sequence Number 2
Notes
Date Text
2018-02-27 14:11:34RECEIVED CORRECTION AND CHANGED STATUS TO PASSED.
  
  
2018-02-08 10:39:59CODES IN EFFECT:
 FBC = FLORIDA BUILDING CODE 2014 5TH EDITION
 FBC CE = FLORIDA BUILDING CODE ENERGY CONSERVATION 2014
 5TH EDITION
 FBC RE = FLORIDA RESIDENTIAL CODE 2014 5TH EDITION,
 PART VIII ELECTRICAL
 NEC = NFPA 70 2011 EDITION, NATIONAL ELECTRICAL CODE
 FS = FLORIDA STATUTES
  
 ELECTRICAL REVIEW STATUS: DENIED, SEE COMMENTS BELOW.
  
 THIS REVIEW FOR FOUNDATION PERMIT ONLY.
  
 RESPONSE LETTER STATED THAT SHEET E3.0.0 WAS PROVIDED
 TO ADDRESS COMMENTS. HOWEVER, THE SHEET WAS ONLY
 PROVIDED FOR 2 OF THE 3 SETS. THIS SHEET IS REQUIRED
 FOR EACH SET. (FBC 107.2.1) THE PREVIOUS COMMENT IS
 LISTED BELOW, AND THERE IS A NEW COMMENT THAT FOLLOWS
 BASED ON THE SUBMISSION PROVIDED.
  
 1. PROVIDE RISER DIAGRAM, SHOWING ALL DETAILS OF
 SERVICE EQUIPMENT, WIRE AND BREAKER SIZES FOR SERVICE.
 SHOW GEC SIZE AND SYSTEM, SHOW INTERSYSTEM BONDING
 TERMINATION POINT. NEC 215.5, 230, 250.50, 250.94,
 408.30, 695.3; FBC 107.2.1
  
 NEW COMMENT:
  
 2. PLAN STATES THAT THE FEED TO THE RETAIL WIREWAY IS 2
 SETS OF 500 KCMIL ALUMINUM, WHICH IS RATED FOR A TOTAL
 OF 620 AMPS. THIS WIRE WILL BE FUSED AT 800 AMPS, SO
 THE WIRE IS UNDERSIZED. PROVIDE CORRECTION. THIS
 COMMENT WILL NOT HOLD UP THE FOUNDATION PERMIT, BUT
 NEEDS TO BE CORRECTED. NEC 310.15(B)(16)
  
 END OF COMMENTS.
  
 PLEASE NOTE: SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS. WHEN
 RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RESUBMITTAL FORM. ADDITIONALLY, INSERT CORRECTED PAGES
 INTO THE ORIGINAL SUBMITTAL AND REMOVE OR VOID THE
 PREVIOUSLY REVIEWED SHEETS.
  
 SINCERELY,
  
 JOHN PEARSON
 ELECTRICAL PLANS EXAMINER
 561-805-6746
 [email protected]
  