2017-11-03 18:47:34 | NEW GUEST HOUSE (R3) MECHANICAL REVIEW COMMENTS. |
| CODE: FBC 5TH EDITION (2014). |
| |
| |
| NOTE: |
| MECHANICAL REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| MEANS THAT CONTRACTOR WILL PROVIDE REQUIRED INFORMATION |
| AFTER THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO |
| AVOID CONFLICTS/DELAYS. REVISION FEES WILL APPLY. |
| CONTRACTOR TO ADVICE IF PROVISO OPTION IS PREFERRED AT |
| THIS TIME. |
| |
| 1- EQUIPMENT SIZING CALCULATIONS ARE DONE BASED ON THE |
| INFORMATION SUBMITTED IN THE ENERGY CALCULATIONS. |
| ENERGY CALCULATIONS NEED TO BE REVISED. SEE BUILDING |
| REVIEW COMMENTS BELOW. REVISE THE EQUIPMENT SIZING |
| CALCULATIONS ONCE THE ENERGY CALCULATIONS ARE REVISED. |
| SEC. R403.6.1 FBC-ENERGY CONSERVATION, 5TH EDITION |
| (2014). |
| |
| |
| BUILDING REVIEW COMMENTS: |
| 1- ENERGY CALCULATIONS FORM R405-2014 SUBMITTED: |
| A) OWNER OR LEGALLY DESIGNATED AGENT TO CERTIFY AT THE |
| BOTTOM OF THE FORM AS REQUIRED BY SEC. R103.1.1.2 |
| FBC-ENERGY CONSERVATION, 5TH EDITION (2014). |
| |
| B) PROVIDE COMPLETE INFORMATION ON TOP OF FORM, |
| INCLUDING THE OWNER'S NAME AND BUILDER'S NAME. SEC. |
| R101.5.1.1.2 FBC-ENERGY CONSERVATION. |
| |
| C) CONCRETE BLOCK WALL INSULATION R-VALUE SPECIFIED ON |
| ITEM #9 DOESN'T MATCH ARCHITECT'S PLANS. REVISE AS |
| REQUIRED TO MATCH. SEC. R103.2 FBC-ENERGY CONSERVATION. |
| |
| D) CEILING INSULATION R-VALUE AND AREA SPECIFIED ON |
| ITEM #10 DOESN'T MATCH PLANS. REVISE AS REQUIRED TO |
| MATCH. SEC. R103.2 FBC-ENERGY CONSERVATION. |
| |
| E) PROVIDE COMPLETE INSPECTION CHECKLIST DOCUMENTING |
| THE BUILDING COMPONENT CHARACTERISTICS OF THE PROPOSED |
| DESIGN AS REQUIRED BY SEC. R405.4.2 FBC-ENERGY |
| CONSERVATION. |
| |
| F) PROVIDE THE NAME OF THE PERSON COMPLETING THE |
| COMPLIANCE REPORT AS REQUIRED BY SEC. R405.4.2 |
| FBC-ENERGY CONSERVATION. |
| |
| G) THE ENERGY PERFORMANCE LEVEL (EPL) DISPLAY CARD |
| SUBMITTED NEEDS TO BE COMPLETED BY THE BUILDER AS |
| REQUIRED BY SEC. R405.4.3 FBC-ENERGY CONSERVATION. |
| |
| H) THE "SPACES" INFORMATION ON 2 OF 4 SPECIFIES THAT |
| THERE IS A KITCHEN. ACCORDING TO PLANS SUBMITTED THERE |
| IS NOT KITCHEN IN THE GUEST HOUSE. THERE IS SUPPOSED TO |
| BE NO COOKING. NOTE: ZONING DOESN'T ALLOW A KITCHEN FOR |
| THE GUEST HOUSE. REVISE ENERGY CALCULATIONS AS |
| REQUIRED. SEC. R103.2 FBC-ENERGY CONSERVATION. |
| |
| I) THE ROOF TYPE AND MATERIALS SPECIFIED ON PAGE 2 OF 4 |
| DON'T MATCH PLANS. SEE PLANS AND REVISE AS REQUIRED. |
| SEC. R103.2 FBC-ENERGY CONSERVATION. |
| |
| |
| |
| |
| ****PLEASE PROVIDE RESPONSE LETTER TO EXPEDITE THE |
| REVIEW PROCESS. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |
| |