Plan Review Notes
Plan Review Notes For Permit 17080529
Permit Number 17080529
Review Stop P
Sequence Number 2
Notes
Date Text
2018-01-05 09:42:572ND REVIEW: FBC 2014 5TH EDITION
  
 PLUMBING COMMENTS: PREVIOUS COMMENTS NOT COMPLIED. TO
 EXPEDITE APPROVAL I SUGGEST A MEETING TO GO OVER
 COMMENTS SEE MY CONNECT INFO BELOW.
  
 PARTIALLY COMPLIED 3) INDICATE HOW THE MED GAS TANKS
 WILL BE SECURED AND PROTECTED FORM DAMAGE- SECTION
 5.1.3.3.2(7) NFPA 99. PLEASE PROVIDE MANUFACTURE
 SPECIFICATION SHEETS FOR CYLINDER BRACKETS AND A DETAIL
 SHOWING HOW THEY WILL BE SECURED TO THE WALL . PER WPB
 AMEND TO FBC 107.2.1
  
 PARTIALLY COMPLIED 16) SHT. A1.6 - CLARIFY THE ACRONYMS
 "LDV" AND "HDV" ON THE VACUUM SYSTEM. IS THE LOW DUTY
 AND HIGH DUTY THE SAME AS LOW PERSSURE AND HIGH
 PRESSURE PLEASE CLARIFY ON PLAN. PER WPB AMEND TO FBC
 107.2.1
  
 PARTIALLY COMPLIED 17) SHT. A1.7 - SUBMIT A MINIMUM OF
 TWO COPIES OF THE MANUFACTURER'S PRE-INSTALLATION GUIDE
 FOR THE VACUUM PIPING SYSTEM TO BE PROVIDED BY A HENRY
 SCHEIN EQUIPMENT SALES SPECIALIST AS REFERENCED IN THE
 FIRST NOTE IN THE VACUUM SYSTEM NOTES ON THIS DRAWING
 PAGE. WPB AMEND. TO FBC SEC.107.2.1. NO SPECS PROVIDED.
 PLEASE SPECIFY ON PLAN EXACTLY WHAT TYPE OF PIPE AND
 FITTINGS WILL BE USED FOR VACUUM SYSTEM. RIGHT NOW IT
 SAYS USE PVC , EXPERT WHERE PROHIBITED, THE CEILING IS
 INDICATED AS AN AIR PLENUM, CLARIFY ONE TYPE OF PIPE.
 PER WPB AMEND TO FBC 107.2.1
  
 PARTIALLY COMPLIED 25) A BACKFLOW PREVENTER IS REQUIRED
 ON THE WATER SUPPLY AT THE BEVERAGE COUNTER AND ICE
 MAKER. 2014 FBC-PLUMBING SEC.608.16.10. SHOW ON RISER
 DIAGRAM AND PROVIDE SCHEDULE FOR BACFLOW DEVISE AND AIR
 HAMMER ARRESTORS. PER WPB AMEND TO FBC 107.2.1
  
 PARTIALLY COMPLIED 26) A WATER HAMMER ARRESTOR
 CONFORMING TO ASSE 1010 SHALL BE INSTALLED WHERE
 QUICK-CLOSING VALVES ARE UTILIZED ON THE WATER
 DISTRIBUTION SYSTEM.2014 FBC-PLUMBING SEC. 604.9. SHOW
 ON RISER DIAGRAM AND PROVIDE SCHEDULE FOR BACFLOW
 DEVISE AND AIR HAMMER ARRESTORS. PER WPB AMEND TO FBC
 107.2.1
  
 PARTIALLY COMPLIED 27) SHT. P001 - NOTE #16 REFERS TO
 SHT. A1.6 FOR A DETAIL OF A SEDIMENT TRAP. THERE IS NO
 DETAIL ON SHT. A1.6. PLAN SHOWS PT MANUFACTURE SPECS
 SHOWS BT PLEASE CLARIFY. PER WPB AMEND TO FBC 107.2.1
  
 PARTIALLY COMPLIED 29) THE HOT WATER RECIRCULATION
 SYSTEM SHALL COMPLY WITH THE 2014 FBC-PLUMBING
 SEC.607.5 FOR THE REQUIRED PIPE INSULATION. PLACE NOTE
 ON PLUMBING SHEETS REFERRING TO MECHANICAL SPEC-AND
 SHEET NUMBER. PER WPB AMEND TO FBC 107.2.1
  
 NEW COMMENTS:
  
 1. SHT. P003 SHOWS 2 TYPE "N" TANKS, 114 LB AND 200CF.
 SHT. P301 NOTE #11 SHOWS 2 TYPE "G" TANKS OX.@ 251CF,
 21LB AND NO.@ 498CF, 57LB PLEASE CLARIFY. PER WPB AMEND
 TO FBC 107.2.1
  
 2. SHT. P301 THE EXHAUSTS FROM A VACUUM PUMP SERVING A
 VACUUM (FLUID SUCTION) SYSTEM SHALL DISCHARGE
 SEPARATELY TO OPEN AIR ABOVE THE ROOF. PER FBC PL 713.6
  
 3. SHT.P301 NOTE #10 IS NOT SHOWN ON THE FLOOR PLAN
 PLEASE CLARIFY . PER WPB AMEND TO FBC 107.2.1
  
 4. SHT. P201 # 9+10 ARE SHOWN ON FLOOR PLAN BUT THERE
 NOT SHOWN ON THE NOTES PLEASE CLARIFY. PER WPB AMEND TO
 FBC 107.2.1
  
 5. SHT. P201 WHAT IS #7 ON THE FLOOR PLAN IT DOES NOT
 MATCH THE NOTE PLEASE CLARIFY. PER WPB AMEND TO FBC
 107.2.1
  
 6. THE WASHING MACHINE SHALL HAVE A 3" BRANCH DRAIN.
 PER FBC PL 406.2
  
 7. THE WASHING MACHINE SHALL DISCHARGE THROUGH A LINT
 TRAP. PER FBC PL 1003.6
  
 8. THE DRAIN FROM THE VACUUM PUMP TANKS SHALL CONNECT
 DIRECTLY TO THE SANITARY SYSTEM NO INDIRECT WASTE.
 PROVIDE DETAIL FOR DRAINAGE CONNECTION OF VACUUM
 SYSTEM. PER FBC PL 713.7 AND WPB AMEND TO FBC 107.2.1
  
 9. THE FLOOR DRAINS AND FLOOR SINK ARE REQUIRED TO HAVE
 TRAP PRIMER VALVES. PER FBC PL 1002.4
  
 10. SHT. P001 IN THE SCHEDULE GT-1 IS NOT SHOWN ON PLAN
 WHAT IS THIS USED FOR PLEASE CLARIFY. PER WPB AMEND TO
 FBC 107.2.1
  
 11. SHT. P101 NOTE #3 THE 2" HUB DRAIN FOR THE VISTA
 FILTER SYSTEM IS NOT SHOWN ON THE RISER DIAGRAM NEITHER
 IS THE TRAP FOR THE VACUUM SYSTEM DRAIN. PLEASE
 CLARIFY. PER WPB AMEND TO FBC 107.2.1
  
 12. SHT. P003 ON THE MED GAS RISER IT SHOWS A HIGH
 PRESSURE VACUUM PUMP PLEASE CLARIFY. PER WPB AMEND TO
 FBC 107.2.1
  
 13. SHT. A1.7 ON THE SCHEDULE IT SHOWS 13, 13A, 13B,
 13C, AND 15A CONNECTING TO NATURAL GAS WHICH STATES NOT
 USED. PLEASE CLARIFY. PER WPB AMEND TO FBC 107.2.1
  
 14. SHT. A1.7 PLEASE PROVIDE DRAWINGS BY HENRY SCHIEN
 OR REMOVE NOTE FROM PLAN. PLEASE CLARIFY. PER WPB AMEND
 TO FBC 107.2.1
  
  
 PLEASE NOTE THAT SUBMITTAL OF ADDITIONAL AND/OR REVISED
 MATERIALS MAY RESULT IN NEW PLAN REVIEW COMMENTS.
 WHEN RESUBMITTING, IT IS HELPFUL TO PROVIDE A RESPONSE
 LETTER ADDRESSING EACH ITEM ALONG WITH THE CITY
 RE-SUBMITTAL FORM. PLEASE, ADDITIONALLY, INSERT
 CORRECTED PAGES INTO TO SUBMITTAL AND REMOVE OR VOID
 THE PREVIOUSLY REVIEWED SHEETS.
  
 GEORGE JOHNSON
 PLUMBING PLANS EXAMINER
 CITY OF WEST PALM BEACH
  561-805-6711
 [email protected]
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  
  