2017-08-09 11:12:38 | 1) PLACE THE PSI OF THE SYSTEM ON BOTH SETS OF PLANS. | | 2014 FBC-FUEL GAS SEC.402.3. | | 2) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES | | USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE | | PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM | | THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE | | DESIGN OF THIS GAS SYSTEM. REFER TO THE 2014 FBC-FUEL | | GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4 | | (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2412.4, | | G2412.8, G2413.1, G2413.2, & G2413.3. | | 3) COPPER SHALL NOT BE USED IF THE GAS CONTAINS MORE | | THAN AN AVERAGE OF 0.3 GRAINS OF HYDROGEN SULFIDE PER | | 100 STANDARD CUBIC FEET OF GAS.SUPPLY INFORMATION FROM | | FLORIDA PUBLIC UTILITIES STATING THE HYDROGEN SULFIDE | | CONTENT IS LESS THE 0.3 GRAINS PE 100 STANDARD CUBIC | | FEET OF GAS. 2014 FBC-FUEL GAS SEC. 403.4.3. | | | | | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | PLUMBING PLAN REVIEW | | 561-805-6692 | | [email protected] | | |
|