Plan Review Notes
Plan Review Notes For Permit 17070634
Permit Number 17070634
Review Stop G
Sequence Number 1
Notes
Date Text
2017-07-24 06:27:111.) LIST THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL
 BTU LOAD ON THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS
 SECS.401.8 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4
 (37) OR 2014 FBC-RES. SEC. G2413.
 2.) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2014
 FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G
 2413.3.
 3.) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE 2014
 FBC-FUEL GAS CODE SEC.304.1, 614.5 (CLOTHES DRYERS) OR
 2014 FBC-RES. SEC. G 2407.1 AND G2439.4 (CLOTHES
 DRYERS).
 4) SHOW THE LOCATION OF ALL MP (STEP-DOWN) REGULATORS.
 A LISTED SHUTOFF VALVE SHALL BE INSTALLED IMMEDIATELY
 AHEAD OF EACH MP REGULATOR. FBC-FUEL GAS SEC.409.4,
 FBC-RESIDENTIAL SEC. G 2420.4.
 5) ). SUBMIT TWO COPIES OF A HOUSE PLAN SHOWING THE
 LOCATION OF THE TANKLESS WATER HEATER AND THE LOCATION
 AND DISTANCE OF ANY OPERABLE DOORS OR WINDOWS IN
 RELATION TO THE WATER HEATER. THE LOCATION OF THE WATER
 HEATER SHALL COMPLY WITH THE MANUFACTURER'S
 INSTALLATION INSTRUCTIONS. THE HOUSE PLAN CAN BE HAND
 DRAWN. WPB AMEND. TO FBC SEC. 107.2.1.
 6) ) INDICATE ON THE PLAN IF THE TANKLESS WATER HEATER
 IS REPLACING AN EXISTING TANKLESS WATER HEATER OR IS IT
 REPLACING A STORAGE TANK TYPE WATER HEATER OR IS IT
 BEING ADDED TO THE EXISTING HOT WATER SYSTEM? INDICATE
 ON THE APPLICATION IN THE DESCRIPTION OF WORK.
 7) SUBMIT TWO COPIES OF THE APPLICABLE SIZING TABLES
 USED TO SIZE THE GAS SYSTEM OR PLACE A NOTE ON THE
 PLANS/DRAWINGS SPECIFYING WHICH SIZING TABLE(S) FROM
 THE GAS CODE OR OTHER STANDARD THAT WERE USED IN THE
 DESIGN OF THIS GAS SYSTEM. REFER TO THE 2014 FBC-FUEL
 GAS SECS. 401.4, 401.8 THRU 402.6.1 AND TABLES 402.4
 (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2412.4,
 G2412.8, G2413.1, G2413.2, & G2413.3.
 8) SUBMIT MANUFACTURER?S SPECIFICATIONS FOR THE
 PRESSURE REGULATORS. REGULATORS INSTALLED ON THE
 EXTERIOR OF THE BUILDING SHALL BE APPROVED FOR OUTDOOR
 INSTALLATION. 2014 FGC SEC.410.1.
 9) SUBMIT TWO COPIES OF THE INSTALLATION MANUAL FOR THE
 TANKLESS WATER HEATER. 2014 FBC-FUEL GAS SEC. 301.3.
 10) THE MODEL OF THE GAS STOVE LISTED ON THE GAS RISER
 DOES NOT MATCH THE SUBMITTED MANUFACTURER'S
 SPECIFICATIONS. CLARIFY.
 11) SUBMIT A FLOOR PLAN SHOWING THE LOCATION OF ALL
 APPLIANCES. THE FLOOR PLAN CAN BE HAND DRAWN. WPB
 AMEND. TO FBC SEC. 107.2.1.
  
 NOTE: THE USE AND CARE GUIDE FOR THE DRYER IS NOT
 NECESSARY FOR REVIEW. PLEASE REMOVE FROM THE DOCUMENTS.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  
  
  
  
  
  
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved