2017-07-13 02:46:321) SUBMIT TWO COPIES OF THE MANUFACTURER'S
 SPECIFICATIONS FOR THE HEAT PUMP.WPB AMEND. TO FBC SEC.
 107.2.1.
 2) THE HEAT PUMP SHALL COMPLY WITH 2014 FBC-ENERGY SEC.
 R403.9.1 - REQD. ON-OOF SWITCH MOUNTEDD ON OUTSIDE OF
 HEATER.
 3) THE HEAT PUMP SHALL HAVE A MINIMUM COP OF 4.0 WHEN
 TESTED IN ACCORDANCE WITH AHRI 1160. 2014 FBC-ENERGY
 SEC. R403.9.1.2.
 4) TIME SWITCHES OR OTHER CONTROL METHOD TO
 AUTOMATICALLY TURN OFF AND ON HEATERS AND PUMPS
 ACCORDING TO A PRESET SCHEDULE SHALL BE INSTALLED ON
 ALL HEATERS AND PUMPS. 2014 FBC-ENERGY
 SEC.R403.9.2.(SEE EXCEPTION #3 ALSO).
  