2017-05-30 15:21:35 | 1ST REVIEW FBC-2014 MECHANICAL |
| PERMIT #17050836 |
| 5/20/17 |
| |
| RESULTS: DENIED. |
| |
| 1) THE $65,000.00 VALUE LISTED ON THE PERMIT |
| APPLICATION APPEARS VERY LOW FOR THE SCOPE OF THE |
| PROPOSED PROJECT. PLEASE SEE SECTION 109.3 FBC- |
| BUILDING PERMIT VALUATION. FOR PERMITTING PURPOSES, |
| VALUATION OF BUILDINGS AND SYSTEMS SHALL BE TOTAL |
| REPLACEMENT VALUE TO INCLUDE STRUCTURAL, ELECTRIC, |
| PLUMBING, MECHANICAL, INTERIOR FINISH, RELATIVE SITE |
| WORK, ARCHITECTURAL AND DESIGN FEES, |
| |
| MARKETING COSTS, OVERHEAD AND PROFIT; EXCLUDING ONLY |
| LAND VALUE. VALUATION REFERENCES MAY INCLUDE THE LATEST |
| PUBLISHED DATA OF NATIONAL CONSTRUCTION COST ANALYSIS |
| SERVICES (MARSHALL-SWIFT, MEANS, ETC.), AS PUBLISHED BY |
| INTERNATIONAL CODE CONGRESS. FINAL BUILDING PERMIT |
| VALUATION SHALL BE SET BY THE BUILDING OFFICIAL. PLEASE |
| NOTE THAT THE VALUE FOR MECHANICAL SHALL INCLUDE THE |
| LABOR, |
| |
| MATERIALS, AND EQUIPMENT FOR BOTH TENANT SPACES AS |
| SHOWN ON THE PLANS. |
| |
| 2) C-7: IN ADDITION TO THE ROOF HATCH FOR THE HOME |
| GOODS OCCUPANCY, A ROOF HATCH AND PERMANENT LADDER IS |
| REQUIRED FOR THE ADJACENT TENANT. PLEASE SHOW THE |
| LOCATION OF THE HATCH AND PROVIDE PERMANENT LADDER |
| DETAILS FOR ACCESS TO BOTH ROOFS IN ACCORDANCE WTH |
| SECTIOON 306.4. |
| |
| 3) M-1: A THOROUGH REVIEW OF THE AC AND ENERGY |
| CALCULATIONS CANNOT BE PERFORMED WITHOUT O/A |
| CALCULATIONS AND EQUIPMENT SCHEDULES FOR RTU'S 1, 3 & |
| 5. PLEASE PROVIDE THE CALCULATIONS AND SCHEDULES ON THE |
| PLANS. |
| |
| 4) M-1: THE HEATING COIL SIZING CALCULATIONS FOR RTU'S |
| 2, 4, 8, 9, & 10 INDICATE THAT 18 KW HEATERS SELECTED |
| ARE OVERSIZED. |
| |
| 5) M-1: THE EFFICIENCY RATINGS LISTED IN THE ENERGY |
| CALCS FOR RTU'S 2, 4, 8, 9 & 10 ARE HIGHER THAN THE |
| RATINGS IN THE SCHEDULE. |
| |
| 6) M-2: DUCT SMOKE DETECTORS ARE REQUIRED FOR ALL RTU |
| SYSTEMS SHOWN ON THE PLANS INCLUDING RTU'S 1, 3, 5, 6 & |
| 7. PROVIDE SYMBOLS ON THE PLANS TO SHOW THEIR |
| LOCATIONS. PLEASE NOTE THAT THE REQUIREMENT FOR THE 5.0 |
| TON SYSTEMS CAN BE WAIVED IF MANUFACTURER'S |
| SPECIFICATIONS INDICATE THE SYSTEMS ARE NOT CAPABLE OF |
| PRODUCING OVER 2000 CFMS OF SUPPLY AIR- SECTION |
| 606.2.1. |
| |
| 7) M-4: PROVIDE COMPLERE ENGINEERING AND THE WIND LOAD |
| DESIGN CRITERIA FOR INSTALLATION OF THE NEW AND |
| REPLACED RTU'S- SECTION 301.15. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 401 CLEMATIS STREET |
| WEST PALM BEACH FL 33401 |
| 561-805-6719 |
| [email protected] |
| |