2017-03-15 09:26:15 | MAXIMUM BUILDING HEIGHT: 30 FEET. | | | | HEIGHT OF STRUCTURE MEANS THE VERTICAL DISTANCE FROM | | THE AVERAGE ELEVATION OF THE FINISHED GRADE OF THE | | STRUCTURE TO THE HIGHEST PORTION OF THE STRUCTURE, | | SUBJECT TO SPECIFIED HEIGHT REQUIREMENTS OF THIS | | CHAPTER. FOR BUILDINGS, THE HEIGHT SHALL BE MEASURED AS | | THE VERTICAL DISTANCE FROM THE AVERAGE ELEVATION OF THE | | FINISHED GRADE OF THE BUILDING TO THE HIGHEST POINT OF | | THE TOP OF THE STRUCTURE OF A FLAT ROOF, OR TO THE DECK | | LINE OF A MANSARD ROOF, OR TO THE MEAN HEIGHT LEVEL | | BETWEEN EAVES AND RIDGE FOR GABLE, HIP, AND GAMBREL | | ROOFS. | | | | THE ELEVATION DRAWINGS NEED TO SHOW THE BUILDING HEIGHT | | MEASURED FROM THE FINISHED GRADE, NOT THE GARAGE FLOOR | | OR THE FINISHED FLOOR. | | | | PAUL GREILICH, SENIOR PLANNER | | 561-822-1443 | | [email protected] |
|