2017-05-09 04:53:04 | 1) AS A NOTE OF INFORMATION, A SEPARATE PERMIT WILL BE |
| REQUIRED FOR THE NEW BACKFLOW PREVENTER LOCATED AT THE |
| NEW WATER METER. THE DEVICE SHALL BE LEAD- FREE AND |
| COMPLY WITH THE CITY OF WPB CROSS-CONNECTION CONTROL |
| MANUAL AND MUST ALSO BE ON THE UNIVERSITY OF SOUTHERN |
| CALIFORNIA'S (USC) LIST OF APPROVED DEVICES. TWO COPIES |
| OF THE MANUFACTURER'S SPECIFICATIONS SHALL BE SUBMITTED |
| AT THE TIME OF PERMIT APPLICATION. 2014 FBC-PLUMBING |
| SEC.605.2.1. THE CITY OF WPB CROSS-CONNECTION MANUAL |
| CAN BE VIEWED AT HTTP://WPB.ORG/UTILITIES/BACKFLOW. |
| 2) SHT. A 8.02 - DETAIL #3 - THE SIDE WALL GRAB BAR |
| NEXT TO THE WATER CLOSET SHALL BE LOCATED PER 2014 |
| FBC-ACCESS.SEC. 604.5.1 & FIGURE 604.5.1. THE GRAB BAR |
| SHALL EXTEND A MINIMUM OF 54 INCHES FROM THE REAR |
| WALL.THE DETAIL SHOWS THE GRAB BAR 10 1/2 INCHES FROM |
| THE REAR WALL WHICH WILL PRODUCE 52 1/2 INCHES FROM THE |
| REAR WALL USING A 42 INCH BAR AND A MINIMUM OF 54 |
| INCHES IS REQUIRED. 2ND REQUEST. |
| 3) SHT. A 8.02 - DETAILS #3 & #4 - THE TOILET PAPER |
| DISPENSER SHALL BE LOCATED 7 INCHES MINIMUM AND 9 |
| INCHES MAXIMUM TO THE CENTER OF THE FIRST TOILET PAPER |
| ROLL, NOT TO THE CENTER OF THE DOUBLE ROLL DISPENSER AS |
| SHOWN ON THE PLANS.FBC-ACCESS SEC.604.7. 2ND REQUEST. |
| 4) THE DETAIL OF THE HOT WATER RECIRCULATING SYSTEM ON |
| DETAIL #1 ON SHT.P0.1 DOES NOT APPEAR TO COMPLY WITH |
| 2014 FBC-PLUMBING SEC.607.2.2. I DO NOT SEE A HOT WATER |
| RETURN LINE COMING FROM THE FIXTURES BACK TO THE WATER |
| HEATERS. PLEASE REFER TO THE FOLLOWING TEXT FROM THE |
| PLUMBING CODE: |
| 607.2.2 RECIRCULATING PUMP. |
| WHERE A THERMOSTATIC MIXING VALVE IS USED IN A SYSTEM |
| WITH A HOT WATER RECIRCULATING PUMP, THE HOT WATER OR |
| TEMPERED WATER RETURN LINE SHALL BE ROUTED TO THE COLD |
| WATER INLET PIPE OF THE WATER HEATER AND THE COLD WATER |
| INLET PIPE OR THE HOT WATER RETURN CONNECTION OF THE |
| THERMOSTATIC MIXING VALVE. |
| 5) THE DESIGN OF THE GREASE INTERCEPTOR SHALL COMPLY |
| WITH THE CITY OF WEST PALM BEACH STANDARD DRAWING GS-7 |
| FOR CONCRETE TANKS AND DRAWING GS-7.1 FOR |
| HYDR-MECHANICAL TANKS. I HAVE INCLUDED COPIES OF THESE |
| STANDARD DRAWINGS IN THE PERMIT APPLICATION SUBMITTAL |
| PACKAGE FOR YOUR PERUSAL. AS A NOTE OF INFORMATION, THE |
| INTERCEPTOR SHALL BE PERMITTED UNDER A SEPARATE PERMIT. |
| ENSURE THE SIZE AND LOCATION OF THE FLOW THROUGH HOLE |
| IN THE BAFFLE COMPLIES WITH THE CITY'S STANDARD |
| DRAWING. |
| |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| PLUMBING PLAN REVIEW |
| 561-805-6692 |