2017-02-21 10:12:20 | 1ST REVIEW FBC-2014 MECHANICAL |
| PERMIT #17020696 |
| 2/21/17 |
| |
| 1) PLEASE ADD THE REPLACEMENT OF THE 14 EXHAUST FANS TO |
| THE WORK DESCRIPTION ON THE APPLICATION, AND ADJUST THE |
| VALUE ACCORDINGLY- SECTION 109.3 WPB AMENDMENTS TO THE |
| FBC. |
| |
| 2) I AM CHALLENGING THE $250,000 JOB VALUE FOR THE |
| PROPOSED PROJECT BASED ON COST VALUATION TABLES |
| PUBLISHED BY MARSHALL & SWIFT VALUATION SERVICE. AS |
| LISTED IN THE TABLES THE THE REPLACEMENT OF THE HEAT |
| PUMPS AND DUCTWORK ALONE WOULD AMOUNT TO APPROXIMATELY |
| $250,000- SEE SECTION 53 PAGE 4. PLEASE PROVIDE AN |
| ITEMIZED COST BREAKDOWN THAT INCLUDES THE COOLING |
| TOWER, THE PUMPS, THE BOILER, THE DUCTWORK, THE PIPING |
| AND CONTROLS, THE EXHAUST FANS, AND THE COOLING TOWER |
| SUPPORT STRUCTURE, STAIRS AND CATWALK. |
| |
| 3) PROVIDE THE WIND LOAD DESIGN CRITERIA FOR |
| INSTALLATION OF ALL THE ROOFTOP FANS AND THE COOLING |
| TOWER, AND ENGINEERED DRAWINGS AND DETAILS FOR |
| INSTALLATION OF THE COOLING TOWER AND SUPPORT |
| STRUCTURE- SECTION 301.15. |
| |
| 4) PROVIDE A LIST OF CODES AND STANDARDS USED IN THE |
| DESIGN OF THE PROJECT. |
| |
| 5) NEW BOILER: A) PROVIDE A COMPLETE EQUIPMENT SCHEDULE |
| FOR THE BOILER INCLUDING BTUH CAPACITY. B) PROVIDE AN |
| ENLARGED DRAWING SHOWING THE REQUIRED WORKING |
| CLEARANCES AND LENGTH OF THE NEW 10'' FLUE. C) PROVIDE |
| THE TOTAL RUN LENGTH OF THE FLUE AND EXISTING VENT FROM |
| THE BOILER OUTLET TO THE TERMINATION ON THE ROOF. D) |
| SHOW THE VENT TERMINATION ON SHEET M-1. |
| |
| 6) COMMISSIONING FOR THE REPLACED COOLING TOWER AND |
| HEAT PUMPS IS REQUIRED PER SECTION C408.2 FBC-14 ENERGY |
| CONSERVATION. PLEASE SUBMIT A COMMISSIONING PLAN AS |
| OUTLINED IN SECTION C408.2.1. |
| |
| 7) PROVIDE A MECHANICAL DEMOLITION PLANS FOR THE |
| EQUIPMENT ROOM. |
| |
| 8) PROVIDE DUCT HANGING AND CONNECTION DETAILS PER |
| SMACNA HVAC CONSTRUCTION STANDARDS 2005. |
| |
| 9) SUBMIT TWO COPIES OF A FL. PRODUCT APPROVAL AND/OR |
| MIAMI-DADE NOA FOR THE GREENHECK LOUVERS. |
| |
| 10) PLEASE CLARIFY IF THE THE REPLACED HEAT PUMPS (O/A |
| UNITS) ARE PART OF THE SMOKE CONTROL SYSTEM AND ARE |
| BEING USED FOR PRESSURIZATION OF CORRIDORS IN THE EVENT |
| OF FIRE. PLEASE NOTE IF THEY ARE SERVING THAT FUNCTION, |
| THEN SPECIAL INSPECTION OF THE SYSTEMS IS REQUIRED AS |
| NOTED IN SECTION 909.3 FBC-14 BUILDING. |
| |