2016-12-29 08:51:14 | 1) INDICATE ON SPECIFICATIONS THE SIZE OF THE GAS |
| HEATER (BTU LOAD) THAT IS BEING INSTALLED. |
| 2) IS THIS POOL HEATER CONNECTING TO EXISTING PIPING OR |
| IS A NEW GAS SYSTEM OR PIPING BEING INSTALLED? INDICATE |
| SUCH ON THE DOCUMENTS.IF A NEW SYSTEM, COMPLY WITH THE |
| FOLLOWING: |
| |
| 1.) SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS THE |
| LENGTH OF ALL CUT SECTIONS OF PIPE PER 2014 FBC-FUEL |
| GAS, SECS. 402.4.1, 402.4.2. OR 2014 FBC-RES SEC. |
| G2413. |
| |
| 2.) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL |
| PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE |
| CORRUGATED STAINLESS STEEL TUBING (IF APPLICABLE) FOR |
| EACH PIPE SIZE. WPB AMENDMENTS TO FBC SEC.107.2.1. |
| |
| 3.) BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD |
| ON THE SYSTEM. REFER TO THE 2014 FBC-FUEL GAS |
| SECS.401.8 THRU 402.6.1 AND TABLES 402.4 (1) THRU 402.4 |
| (37) OR 2014 FBC-RES. SEC. G2413. |
| |
| 4.) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS |
| METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE |
| OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2014 |
| FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G |
| 2413.3. |
| |
| 5) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM |
| ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. |
| SEC. G2413.2. . |
| |
| 6) IF THIS IS A REPLACEMENT OF AN EXISTING POOL HEATER, |
| INDICATE THE BTU LOAD OF THE EXISTING POOL HEATER BEING |
| REPLACED. WPB AMEND. TO FBC SEC. 107.2.1. |
| |
| NOTE: A SEPARATE GAS PERMIT APPLICATION IS REQUIRED |
| FROM A PROPERLY LICENSED GAS CONTRACTOR FOR THE GAS |
| CONNECTIONS TO THE POOL HEATER. |
| |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| PLUMBING PLAN REVIEW |
| 561-805-6692 |
| [email protected] |
| |
| |