Date |
Text |
2016-12-07 17:25:17 | 1ST REVIEW FBC-2014 MECHANICAL, EXISTING BUILDING CODES |
| PERMIT #16120232 |
| 12/7/16 |
| |
| 1) THE SCOPE OF THE REVISION MUST BE CHANGED TO |
| INDICATE THE CORRECT SCOPE OF THE PROJECT. THERE WERE |
| NO AC PLANS SUBMITTED UNDER EITHER THE MASTER PERMIT |
| #16090343 OR SUB-PERMIT #16110192. ADDITIONALLY, THE |
| VALUE OF THE PROJECT MUST BE INCREASED TO INCLUDE THE |
| COSTS OF THE REPLACED AC SYSTEM AND NEW DUCT LAYOUT- |
| LABOR, MATERIALS, AND EQUIPMENT. |
| |
| 2) SUBMIT AN AC CHANGE OUT FORM FOR THE REPLACED |
| SYSTEM. THE FORM CAN BE FOUND AT THE DEVELOPMENT |
| SERVICES WEBSITE- WWW.CITYOFWPB.COM. |
| |
| 3) REFER TO SECTION 809.2 FBC-14 EXISTING BUILDING CODE |
| AND PROVIDE MINIMUM VENTILATION CALCULATIONS FOR ALL |
| ROOMS AND SPACES PER TABLE 403.3 FBC-14 MECHANICAL. |
| PROVIDE A SCHEDULE THAT INDICATES THE REQUIRED AND |
| PROVIDED CFMS OF OUTDOOR AIR. |
| |
| 4) REFER TO TABLE 403.3 AND PROVIDE EXHAUST VEMTILATION |
| FOR THE ART STUDIO AT A RATE OF 0.7 CFMS PER SQ. FT. |
| PLEASE SEE FOOTNOTE G PERTAINING TO RESTRICTIONS ON |
| RECIRCULATION OF AIR IN THE SPACE. |
| |
| 5) IDENTIFY ALL ROOMS AND SPACES ON THE PLAN. |
| |
| 6) PROVIDE THE SUPPLY CFMS AT THE 6X6 DIFFUSER. |
| |
| 7) PROVIDE WIND LOAD ENGINEERING FOR ANCHORING THE |
| CONDENSER- SECTION 301.15. |
| |
| 8) ALL INFORMATION, DRAWINGS, SPECIFICATIONS AND |
| ACCOMPANYING DATA SHALL BEAR THE NAME AND SIGNATURE OF |
| THE PERSON RESPONSIBLE FOR THE DESIGN- SECTION 107.2.1 |
| WPB AMENDMENTS TO THE FBC. |
| |
| 9) PROVIDE A REVISED ELECTRICAL PLAN |
| |
| 10) PROVIDE A MEANS OF ACCESS FOR MAINTENANCE AND |
| REPLACEMENT OF THE AIR HANDLER WHCIH APPEARS TO BE |
| ABOVE THE CEILING- SECTION 306.1 |
| |
| 11) PROVIDE PRIMARY AND SECONDARY CONDENSATE DISSPOSAL |
| DETAILS- SECTION 307. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |