2017-01-05 11:10:32 | BUILDING PLAN REVIEW |
| 2014 FLORIDA BUILDING CODE W/2010 WEST PALM BEACH |
| AMENDMENTS TO THE FLORIDA BUILDING CODE, CHAPTER 1 |
| ADMINISTRATION |
| |
| CHRISTOPHER S. THROOP, C.B.O. |
| BUILDING PLANS EXAMINER, PX3169 |
| CONSTRUCTION SERVICES DIVISION |
| TEL: 561-805-6726 |
| FAX: 561-805-6676 |
| |
| 2ND REVIEW |
| RESULTS: DENIED |
| ADDRESS THE ATTACHED COMMENTS AND RE-SUBMIT |
| |
| 1. THIS IS A REPAIR TO AN EXISTING BUILDING, (STORAGE |
| STRUCTURE). CHANGE GOVERNING CODES TO 2014 FBC EXISTING |
| BUILDING. |
| 2. WORK COMPLETED WITHOUT PERMIT AS INDICATED ON PLANS. |
| 4X FEE WILL APPLY. |
| 3. ENGINEER OF RECORD (EOR) TO PRODUCE CERTIFICATION |
| LETTER FOR COMPLETED WORK. INCLUDE CERTIFICATION OF |
| WOOD CONNECTORS PREVIOUSLY REVIEWED AND APPROVED BY |
| EOR. |
| 4. CHANGE SCOPE OF WORK TO ACCURATLEY DESCRIBE EXTENT |
| OF WORK COMPLETED WITHOUT PERMIT. IF WINDOWS AND DOORS |
| WERE INSTALLED PROVIDE PRODUCT APPROVALS FOR EACH. |
| 5. FBC 117 - THE BUILDING OFFICIAL MAY REQUIRE TESTS OR |
| TEST REPORTS AS PROOF OF COMPLIANCE. REQUIRED TESTS ARE |
| TO BE MADE AT THE EXPENSE OF THE OWNER, OR AGENT, BY AN |
| APPROVED TESTING LABORATORY OR OTHER APPROVED AGENCY. |
| 6. A PERMIT FOR THE STORAGE STRUCTURE DOES NOT RELIEVE |
| OWNER FROM THE EXISTING 4X FEE IMPOSED FOR WORK |
| PERFORMED ON MAIN HOUSE AND GARAGE. REF: CASE # |
| CE16050796. |
| 7. THE STATED VALUE APPEARS LOW. |
| THE PERMIT VALUATION AND PERMIT FEE MUST BE |
| COMMENSURATE WITH THE VALUATION AND FEE THAT A LICENSED |
| CONTRACTOR WOULD PROVIDE. PLEASE INCREASE THE VALUATION |
| ACCORDINGLY. |
| YOU MAY PROVIDE A COPY OF THE CONTRACT SIGNED BY THE |
| OWNER OR A LIST OF LABOR, MATERIALS AND EQUIPMENT |
| RENTAL TO VERIFY VALUE. |
| |
| 109.3 BUILDING PERMIT VALUATIONS. IF, IN THE OPINION OF |
| THE BUILDING OFFICIAL, THE CLAIMED VALUATION OF |
| BUILDING, ALTERATION, STRUCTURE, ELECTRICAL, GAS, |
| MECHANICAL OR PLUMBING SYSTEMS APPEARS TO BE |
| UNDERESTIMATED ON THE APPLICATION, THE PERMIT SHALL BE |
| DENIED, UNLESS THE APPLICANT CAN SHOW DETAILED, |
| QUANTITY ESTIMATES, AND/OR BONA FIDE SIGNED CONTRACTS |
| (EXCLUDING LAND VALUE) TO MEET THE APPROVAL OF THE |
| BUILDING OFFICIAL. FOR PERMITTING PURPOSES, VALUATION |
| OF BUILDINGS AND SYSTEMS SHALL BE TOTAL REPLACEMENT |
| VALUE TO INCLUDE STRUCTURAL, ELECTRIC, PLUMBING, |
| MECHANICAL, INTERIOR FINISH, RELATIVE SITE WORK, |
| ARCHITECTURAL AND DESIGN FEES, MARKETING COSTS, |
| OVERHEAD AND PROFIT; EXCLUDING ONLY LAND VALUE. |
| VALUATION REFERENCES MAY INCLUDE THE LATEST PUBLISHED |
| DATA OF NATIONAL CONSTRUCTION |
| COST ANALYSIS SERVICES (MARSHALL-SWIFT, MEANS, ETC.), |
| AS PUBLISHED BY INTERNATIONAL CODE CONGRESS. |
| FINAL BUILDING PERMIT VALUATION SHALL BE SET BY THE |
| BUILDING OFFICIAL. |
| |
| |
| |
| |