2016-10-13 08:48:561) NOTE #1 IN THE SANITARY NOTES STATE THAT THE
 EXISTING UNDERGROUND CAST IRON IS GOING TO BE
 REPLACED.INDICATE ON THE PLAN HOW THE PIPNG WILL BE
 ACCESSED. WILL THE SLAB BE CUT OR WILL THERE BE
 TUNNELING UNDER THE SLAB? IF TUNNELING WILL BE DONE THE
 FOLLOWING INFORMATION SHALL BE SUBMITTED.
 PLUMBING REPAIR TUNNEL WORK
 2) SHOW HOW THE NEW PIPE WILL BE SUPPORTED, THE TYPE OF
 ADAPTERS USED FOR THE CONNECTIONS TO EXISTING PIPE, AND
 THE LOCATIONS OF REQUIRED CLEANOUTS. DETAILS AND
 BACKFILLING PROCEDURES SHALL BE SUBMITTED THAT CLEARLY
 SHOW HOW THE STRUCTURAL INTEGRITY OF THE CONCRETE SLAB
 WILL BE MAINTAINED DURING EXCAVATION AND BACKFILLING.
 STRUCTURAL FOAM IS NOT PERMITTED FOR BACKFILL BELOW
 GROUND PER THE FLORIDA BUILDING CODE, RESIDENTIAL,
 SECTION 318.8 AND THE FLORIDA BUILDING CODE, BUILDING,
 SECTION 2603.9.
 3) SUBMIT A SLAB REPAIR DETAIL IF THE SLAB WILL BE CUT
 TO ACCESS THE PIPE.SHOW THE WIDTH OF THE REPAIR AREA,
 THE SIZE OF THE DOWELS TO BE INSTALLED, THE EMBEDMENT
 DEPTH OF THE DOWELS INTO THE EXISTING AND THE NEW SLAB
 REPAIR, THE SPACING OF THE DOWELS, AND THE ANCHORING
 METHOD OF THE DOWELS INTO THE EXISTING SLAB.
 4) THE DRINKING FOUNTAIN,THE HANDICAP LAVATORY AND THE
 JANITOR SINK ARE ALL DRAWN ON THE RISER AS BEING FLOOR
 MOUNTED FIXTURES AND WOULD BE S- TRAPPED. THESE SHOULD
 BE DRAWN AS STACKED AND VENTED FIXTURES. CLARIFY.
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved