2016-09-29 08:30:05 | ELECTRICAL REVIEW NOTES |
| REVIEWED FOR COMPLIANCE WITH: |
| ELECTRICAL REVIEW NOTES |
| REVIEWED FOR COMPLIANCE WITH: |
| 5TH EDITION FBC 2014 & NFPA 70 2011 (NEC) |
| |
| PROJECT NAME: |
| JOB ADDRESS: |
| DESCRIPTION: REPLACE METER CAN AND 2 LAKE AERATOR |
| CONTROLLERS |
| MASTER PERMIT: 16090909 |
| |
| BELOW PLEASE FIND A LIST OF REQUIRED CORRECTIONS. |
| ADDITIONAL CORRECTIONS MAY BE REQUIRED AFTER REVIEW OF |
| SUBMITTED CORRECTIONS. |
| |
| 1. NEC 682.11: YOU SHALL SUBMIT A SITE DIAGRAM/PLAN |
| SHOWING THE LOCATION OF EVERY ELECTRICAL COMPONENT |
| ASSOCIATED WITH THE PERMIT TO ASCERTAIN COMPLIANCE WITH |
| RELATION TO THE SHORELINE AND THE ELECTRICAL DATUM |
| PLANE. |
| 2. ALL LIVE PARTS SHALL BE ELEVATED 12? ABOVE THE EDP & |
| SERVICE EQUIPMENT SHALL DISCONNECT WHEN THE WATER RISES |
| TO THE EDP. |
| 3. NEC 682.33(A): YOU SHALL SHOW ON THE SITE PLAN THE |
| REQUIRED EQUIPOTENTIAL BONDING PLANE. |
| |
| WHEN RESUBMITTING, FOR A QUICKER RETURN ON YOUR |
| RE-SUBMITTAL, PLEASE PROVIDE A RESPONSE LETTER |
| (NARRATIVE) ADDRESSING EACH ITEM AND THE PAGE NUMBER |
| WHERE THE CORRECTIONS APPEAR ALONG WITH THE STANDARD |
| CITY RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| CORRECTED PAGES INTO THE SUBMITTAL PACKAGE. MARK VOID |
| AND LEAVE THE PREVIOUSLY REVIEWED SHEETS FOR |
| COMPARATIVE REVIEW. CLOUDING THE CHANGES WILL BE |
| GREATLY APPRECIATED. |
| |
| IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO |
| CONTACT ME DIRECTLY. |
| |
| THANK YOU, |
| MIKE ALBARRAN |
| ELECTRICAL PLANS EXAMINER |
| PH: 561-805-6746 |
| EMAIL: [email protected] |
| |
| |