Plan Review Notes
Plan Review Notes For Permit 16090175
Permit Number 16090175
Review Stop G
Sequence Number 1
Notes
Date Text
2016-09-10 04:16:201) SUBMIT A SITE PLAN SHOWING THE LOCATION AND CAPACITY
 OF THE LP TANK. SHOW THE DISTANCE OF THE LP TANK FROM
 THE BUILDING WALL. COMPLY WITH NFPA 58 SEC.6.3.2.3 - NO
 PART OF AN UNDERGROUND OR MOUNDED ASME CONTAINER
 SHALL BE LESS THAN 10 FT (3 M) FROM A BUILDING OR LINE
 OF ADJOINING PROPERTY THAT CAN BE BUILT UPON
 2) SHOW THE DISTANCE OF THE LP TANK TO THE
 DRIVEWAY.INSTALLATIONS WITHIN 10 FT (3 M) OF A PUBLIC
 VEHICULAR THOROUGHFARE OR DESIGNATED PARKING LOCATION
 SHALL BE PROVIDED WITH
 VEHICULAR BARRIER PROTECTION FOR THE CONTAINER?S
 FITTING HOUSING, COMPLY WITH NFPA 58 SEC.6.6.6.1 (C) &
 (E) - THE INSTALLATION OF A BURIED CONTAINER SHALL
 INCLUDE PROTECTIONFOR THE CONTAINER AND PIPING AGAINST
 PHYSICAL DAMAGE
 FROM VEHICULAR TRAFFIC.
 3) SUBMIT COMPLETE MANUFACTURER'S
 SPECIFICATIONS/INSTALLATIONN MANUAL FOR REVIEW. THE
 GENERATOR SHALL BE UL 2200 LISTED AND BE INSTALED IN
 ACCORDANCE WITH THE MANUFACTURER'S INSTALLATION
 INSTRUCTIONS AND NFPA 37. 2014 FBC-FUEL GAS SEC.616.1.
 4) SUBMIT DETAILS AS TO HOW THE LP TANK WILL BE
 ANCHORED TO PREVENT FLOTATION. NFPA 58 SEC. 6.6.1.6.
 5) SHOW THE TYPE OF TANK ( DOT OR ASME ), THE LOCATION
 TO ADJACENT PROPERTY LINES, THE DISTANCE OF THE TANK
 FROM ALL SOURCES OF IGNITION, OTHER CONTAINERS,
 BUILDINGS, AND THE LOCATION OF ANY BUILDING OPENINGS
 BELOW THE RELIEF VALVE OF THE TANK PER NFPA 58, TABLE
 3-2.2.2.
 6) SHOW THE TYPE OF PIPE MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE CORRESPONDING EHD NUMBER OF THE
 CORRUGATED STAINLESS STEEL TUBING (IF APPLICABLE) FOR
 EACH PIPE SIZE. WPB AMENDMENTS TO FBC SEC.107.2.1.
 7) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (GAS
 METER / MP REGULATOR / LP TANK) TO THE MOST REMOTE
 OUTLET IN THE BUILDING AND / OR SYSTEM PER THE 2014
 FBC-FUEL GAS SEC.402.4.1 OR 2014 FBC-RES. SEC. G
 2413.3.
 8) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES.
 SEC. G2413.2.
 9.) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved