Date |
Text |
2016-10-28 12:12:41 | 2ND REVIEW FBC-2014 MECHANICAL |
| PERMIT #16081096 |
| 10/28/16 |
| |
| 1) THE AC CALCULATIONS FOR RTU-3A INDICATE 8.6 KW HEAT |
| REQUIRED, THE SCHEDULE INDICATES 4.0 KW PROVIDED. RTU- |
| 3B- 11.66 KW REQUIRED, 6.0 KW PROVIDED. |
| |
| 2) SHEET M1.1: IT APPEARS THAT THERE IS NO WAY FOR THE |
| AIR SUPPLIED TO ALL THE FLEX, OFFICE, SALES, MANGEMENT |
| ROOMS ETC. TO RETURN TO RTU-1. THE ARCHITECTURAL |
| DRAWINGS APPEAR TO INDICATE THE FRAMED AND GLASS WALLS |
| ARE SPANNING FROM FLOOR TO UNDERSIDE OF DECK WHICH |
| WOULD CLOSE OFF THE AIRWAYS- SEE SHEETS A1.1, A3.1.2, & |
| A5.0.1. |
| |
| 3) IN RESPONSE TO COMMENT #13 FROM THE 1ST REVIEW, THE |
| ENGINEER IS REQUESTED THE WIND LOAD ENGINEERING FOR |
| ANCHORING THE NEW RTU'S TO BE DEFERRED SUBMITTALS WHICH |
| IS ACCEPTED. PLEASE REVIEW THE FOLLOWING REQUIREMENTS |
| PER SECTION 107.3.4.2 WPB AMENDMENTS TO THE FBC: |
| |
| A) DEFERRED SUBMITTALS. FOR THE PURPOSES OF THIS |
| SECTION, DEFERRED SUBMITTALS ARE DEFINED AS THOSE |
| PORTIONS OF THE DESIGN THAT ARE NOT SUBMITTED AT THE |
| TIME OF THE |
| APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| REVIEW BY THE BUILDING OFFICIAL. |
| DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| OFFICIAL. |
| |
| B)107.3.4.1 PRODUCT APPROVALS. THOSE PRODUCTS WHICH ARE |
| REGULATED BY THE DCA RULE 9N-03 SHALL BE REVIEWED AND |
| APPROVED IN WRITING BY THE DESIGNER OF RECORD PRIOR TO |
| SUBMITTAL FOR JURISDICTIONAL APPROVAL. |
| FROM THE 1ST REVIEW, THE ENGINEER IS REQUESTED THE WIND |
| LOAD ENGINEERING FOR ANCHORING THE NEW RTU'S TO BE |
| DEFERRED SUBMITTALS. PLEASE REVIEW THE FOLLOWING |
| REQUIREMENTS PER SECTION |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |