Date |
Text |
2017-03-27 10:37:57 | RESIDENTIAL (R3) CHANGE OF USE/ALTERATION MECHANICAL |
| REVIEW CHECKLIST. |
| CODE: FBC 5TH EDITION (2014). |
| |
| NOTE: |
| MECHANICAL REVIEW MAY BE APPROVED WITH PROVISO. PROVISO |
| MEANS THAT CONTRACTOR MAY SUBMIT REQUIRED INFORMATION |
| AFTER THE PERMIT IS ISSUED BUT BEFORE INSPECTIONS TO |
| AVOID CONFLICTS/DELAYS. REVISION FEES WILL APPLY. |
| CONTRACTOR TO ADVICE IF PROVISO OPTION IS PREFERRED AT |
| THIS TIME OR IF RE-SUBMITTING CORRECT INFORMATION. |
| |
| 1- REVISED EQUIPMENT CALCULATIONS FOR THE REAR |
| STRUCTURE NEEDS TO BE REVISED. SELECTED EQUIPMENT NEEDS |
| TO BE CHANGED. "THE CORRESPONDING LATENT CAPACITY OF |
| THE EQUIPMENT SHALL NOT BE LESS THAN THE CALCULATED |
| LATENT LOAD". SEC. R403.6.1.1 FBC-ENERGY CONSERVATION, |
| 5TH EDITION (2014). |
| |
| 2- EQUIPMENT SHOWN ON DRAWING M1 FOR THE REAR STRUCTURE |
| DOESN'T MATCH EQUIPMENT SHOWN ON THE REVISED EQUIPMENT |
| SIZING CALCULATIONS. REVISE AS REQUIRED TO MATCH , |
| INCLUDING THE SEER. SEC. R403.6.1.1 FBC-ENERGY |
| CONSERVATION. |
| |
| 3- ONLY THE SUMMARY SHEET OF THE EQUIPMENT SIZING |
| CALCULATIONS WAS SUBMITTED. PROVIDE THE COMPLETE |
| EQUIPMENT SIZING CALCULATIONS FOR THE MAIN HOUSE AND |
| FOR THE REAR STRUCTURE. SEC. R403.6.1.1 FBC-ENERGY |
| CONSERVATION. |
| |
| |
| ****PLEASE PROVIDE RESPONSE LETTER ADDRESSING EACH |
| COMMENT TO EXPEDITE THE REVIEW PROCESS. |
| ****PLEASE INSERT ANY REVISED DRAWING AND REMOVE OLD |
| DRAWING. DON'T STAPLE OLD DRAWINGS. SUBMITT OLD |
| DRAWINGS FOR REFERENCE. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |