2016-10-17 17:31:33 | 2ND REVIEW FBC-2014 MECHANICAL |
| PERMIT #16080659 |
| 10/17/16 |
| |
| 1) THE AC CALCULATIONS MUST BEAR THE SIGNATURE AND SEAL |
| OF THE ENGINEER WHO PREPARED THEM- SECTION C403.2.1 |
| FBC-14 ENERGY CONSERVATION, AND SECTION 61G15-23.002 |
| FAC. |
| |
| 2) THE PLAN DOES NOT CLEARLY INDICATE HOW AIR WILL BE |
| RETURNED TO THE RTU FROM THE TECH ROOM, THE WEST AND |
| NORTH OFFICES, THE RECEPTION ROOM, THE WORK AREAS, AND |
| CORRIDORS. PLEASE REFER TO SHEETS A-1.0 AND A-3.0: THE |
| D WALL TYPE AND THE GLASS PARTITION AND HEADERS ARE |
| SHOWN TO BE SPANNING FROM THE FLOOR TO THE STRUCTURE |
| ABOVE. A) ADVISORY: PLEASE REFER TO SECTION 601.2: |
| CORRIDORS SHALL NOT SERVE AS RETURN DUCTS. |
| |
| 3) PROVIDE THE ROOF PLAN SHEET A1.1 SHOWN IN THE INDEX. |
| |
| 4) THE ARCHITECT HAS REQUESTED THE ENGINEERING FOR |
| INSTALLATION OF THE RTU, CURB ADAPTER, AND ROOF STAND |
| BE DEFFERRED SUBMITTALS. PLEASE NOTE THAT THE |
| ENGINEERING MUST BE SUBMITTED AND APPROVED PRIOR TO |
| INSPECTION OF THE INSTALLATIONS. |
| |
| A) DEFERRED SUBMITTAL: 107.3.4.2 DEFERRED SUBMITTALS. |
| FOR THE PURPOSES OF THIS SECTION, DEFERRED SUBMITTALS |
| ARE DEFINED AS THOSE PORTIONS OF THE DESIGN THAT ARE |
| NOT SUBMITTED AT THE TIME OF THE |
| APPLICATION AND THAT ARE TO BE SUBMITTED TO THE |
| BUILDING OFFICIAL WITHIN A SPECIFIED PERIOD. DEFERRAL |
| OF ANY SUBMITTAL ITEMS SHALL HAVE THE PRIOR APPROVAL OF |
| THE BUILDING OFFICIAL. THE REGISTERED DESIGN |
| PROFESSIONAL IN RESPONSIBLE CHARGE SHALL LIST THE |
| DEFERRED SUBMITTALS ON THE CONSTRUCTION DOCUMENTS FOR |
| REVIEW BY THE BUILDING OFFICIAL. |
| DOCUMENTS FOR DEFERRED SUBMITTAL ITEMS SHALL BE |
| SUBMITTED TO THE REGISTERED DESIGN PROFESSIONAL IN |
| RESPONSIBLE CHARGE WHO SHALL REVIEW THEM AND FORWARD |
| THEM TO THE BUILDING OFFICIAL WITH A NOTATION |
| INDICATING THAT THE DEFERRED SUBMITTAL DOCUMENTS HAVE |
| BEEN REVIEWED AND FOUND TO BE IN GENERAL CONFORMANCE TO |
| THE DESIGN OF THE BUILDING. THE DEFERRED SUBMITTAL |
| ITEMS SHALL NOT BE INSTALLED UNTIL THE DEFERRED |
| SUBMITTAL DOCUMENTS HAVE BEEN APPROVED BY THE BUILDING |
| OFFICIAL. |
| |
| B) DEFERRED SUBMITTAL. 2010 FBC 107.3.4.1 PRODUCT |
| APPROVALS. THOSE PRODUCTS WHICH ARE REGULATED BY THE |
| DCA RULE 9N-03 SHALL BE REVIEWED AND APPROVED IN |
| WRITING BY THE DESIGNER OF RECORD PRIOR TO SUBMITTAL |
| FOR JURISDICTIONAL APPROVAL. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |