Plan Review Notes
Plan Review Notes For Permit 16071059
Permit Number 16071059
Review Stop P
Sequence Number 3
Notes
Date Text
2017-07-14 15:03:501) SHT. A6.08 - THE CLEAR FLOOR SPACE FOR THE LAVATORY
 SHALL BE CENTERED ON THE FIXTURE PER THE FAIR HOUSING
 ACCESSIBILITY GUIDELINES.IN ADDITION, PROVIDE THE CLEAR
 LENGTH X WIDTH DIMENSIONS OF ALL REQUIRED CLEAR FLOOR
 SPACE DIMENSIONS FOR THE FIXTURES PER THE FHAG.
 2) SHT. A6.10 - SHOW THE DIMENSIONS OF THE CLEAR FLOOR
 SPACE FOR THE WATER CLOSET IN THE A1 UNIT MODEL. COMPLY
 WITH FHAG.
 3) SHT. A 6.10 - UNITS A1 & B1 ARE SHOWN AS A TYPE "A"
 & "B" DESIGN SPECIFICATION BATHROOM PER THE FHAG. IF
 THESE ARE "UFAS" UNITS, IDENTIFY THEM AS SUCH. WPB
 AMEND. TO FBC SEC. 107.2.1.
 4) THE LETTTER FROM THE ARCHITECT REGARDING THE TOILET
 FACILITIES FOR WORKERS IS VAGUE AND IS UNACCEPTABLE.
 REFERENCE IS MADE TO A MAINTENANCE RESTROOM BUT THERE
 IS NO MAINTENANCE RESTROOM IN BUILDING #1.SANITARY
 FACILITIES FOR WORKERS IN THE MAINTENANCE AND TRASH
 AREAS OF BUILDING #1 SHALL BE PROVIDED WITHIN 500 FEET
 OF THESE AREAS. 2014 FBC SEC. 403.3.3
 5) SHT. P4.05 - A URINAL IS NOT PERMITTED ON A WET VENT
 THE RISER SHOWS THE URINAL IN THE MEN'S RESTROOM ACROSS
 FROM THE EXERCISE ROOM DISCHARGING INTO A VERTICAL WET
 VENT ABOVE THE LAVATORY. THE URINAL IS TO BE INSTALLED
 ON IT'S OWN STACK & VENTED. 2014 FBC SECS.912.1,
 912.1.1. 3RD REQUEST.
 6) SHT. P2.05B - THE MEN'S AND WOMEN'S RESTROOMS ACROSS
 FROM THE EXERCISE ROOM ARE STILL MISLABELED.PLEASE
 REVISE.
 7) THE LOCATION OF SANITARY RISERS S/24 & S/25 LOCATED
 ACROSS FROM THE LAUNDRY ROOM ON SHT. P2.05B ARE
 REVERSED AS TO THE LAYOUT ON SHT. P4.05, REFER TO
 BUILDING # II, UNIT B1.2ND REQUEST.
 8) THE DETAIL FOR THE "PLENUM RATED" WATER METERS ON
 SHEET P5.00 WILL REQUIRE ADDITIONAL DOCUMENTATION FROM
 THE MANUFACTURER CWE. INFORMATION ON THEIR WEBSITE
 INDICATES THEY DO NOT MANUFACTURE "PLENUM RATED WATER
 METERS". THE MATERIAL COMPOSITION OF THE WATER METERS
 SHALL MEET THE SMOKE- DEVELOPED INDEX AND FLAME SPREAD
 RATING REQUIREMENTS OF ASTM E84 OR UL 723. THE FLAME
 SPREAD INDEX SHALL BE NOT MORE THAN 25 AND THE
 SMOKE-DEVELOPED INDEX SHALL NOT BE MORE THAN 50. 2014
 FBC - MECHANICAL SEC. 602.2.1.2ND REQUEST.
 9) SHT. P1.00 - THE ORIENTATION OF BUILDING # II IN
 RELATION TO THE POINT OF COMPASS ON THE PLAN DOES NOT
 CORRELATE WITH THE ORIENTATION OF BULDING II ON SHT.
 P2.05. CLARIFY. 2ND REQUEST.
  
 NOTE: THE ABOVE CONDITIONS ARE PROVISOS FOR APPROVAL OF
 THESE PLANS FOR PLUMBING PLAN REVIEW. REVISED PLANS
 SHALL BE SUBMITTED FOR REVIEW AND APPROVAL PRIOR TO THE
 ISSUANCE OF THE PLUMBING PERMIT.
 T.LARGE, CHIEF PLUMBING INSPECTOR
 JULY 14TH, 2017.
  
  
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 PLUMBING PLAN REVIEW
 561-805-6692
 [email protected]
  
  