2016-08-29 12:05:55 | 1ST REVIEW FBC-2014 MECHANICAL |
| PERMIT #16071058 |
| ROYAL PALM PLACE, BUILDING-3. |
| |
| 1) THE SUBMITTED AC CALCULATION PACKET DOES NOT INCLUDE |
| THE AHU-A2/CU-2, AHU-A3/CU-3, & AHU-B2/CU-2, SYSTEMS, |
| AND ARE LISTING MIAMI AS THE LOCATION. A) REVIEW THE AC |
| SCHEDULE ON M-4.00 AS THE 4-TON SYSTEM AHU-1 SYSTEM |
| DOES NOT MATCH THE AHU-1 SYSTEM SHOWN ON SHEET M-2.00 |
| IN TERMS OF CAPACITY. B) REFER TO SECTION C403.2.1 |
| FBC-14 ENERGY |
| |
| CONSERVATION: A COOLING AND HEATING CALCULATION SHALL |
| BE SUBMITTED FOR EACH SYSTEM SHOWN ON THE PLAN, AND ALL |
| SUMMARY CALCULATIONS SUBMITTED BY A REGISTERED ENGINEER |
| SHALL BEAR THE SIGNATURE AND SEAL OF THE ENGINEER. SEE |
| ALSO SECTION C407.5.2.3 IF SUBMITTING A TOTAL BUILDING |
| PERFORMANCE ENERGY COMPLIANCE METHOD. |
| |
| 2) SHEETS M-1.09, M-2.00, & M-400: THE SPLIT AC |
| SCHEDULE DOES NOT INCLUDE THE AHU-2, AHU-3, AHU-B2, & |
| AHU-B3 SYSTEMS. |
| |
| 3) SHEETS M2.00 & M-2.01: THE EXCEPTION UNDER SECTION |
| 504.6.1 THAT ALLOWED THE USE OF DRYER BOOSTER FANS HAS |
| BEEN REMOVED FROM THE FBC-14 MECHANICAL CODE. PLEASE |
| SUBMIT MANUFACTURER'S SPECIFICATIONS AND EXHAUST VENT |
| INSTALLATION INSTRUCTIONS. |
| |
| 4) THE PROPOSED BUILDING SHALL BE IN COMPLIANCE WITH |
| THE FBC-14 ENERGY CONSERVATION CODE. REFER TO SECTIONS |
| C101.2, C101.5, AND C401.2 AND SUBMIT COMPLIANCE |
| MATERIALS AND FORMS. |
| |
| 5) PROVIDE EQUIPMENT SCHEDULES FOR THE APARTMENT |
| OUTSIDE AIR FANS AND MOTORIZED DAMPERS, AND PROVIDE |
| CLEARANCE DISTANCE MEASUREMENTS FOR ALL AIR INTAKES- |
| SECTION 401.4 |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |
| |