2016-08-23 14:13:24 | GEORGE JOHNSON |
| PLUMBING PLANS EXAMINER LL |
| CITY OF WEST PALM BEACH |
| DEVELOPMENT SERVICES |
| BUILDING DIVISION |
| 561-805-6711 |
| [email protected] |
| |
| |
| PLUMBING COMMENTS: 1ST REVIEW |
| |
| 1. SHT A-7 SANITARY RISER SIZE BRANCH TO LAUNDRY . PER |
| WPB AMEND TO FBC 107.2.1 |
| |
| 2. THE STACK, P- TRAP-AND STAND PIPE FOR WASHING |
| MACHINE SHALL BE MIN OF 2IN. PER FBC RES. TABLE P3201.7 |
| |
| 3. AT LEAST ONE OF THE VENTS SHALL EXTEND THROUGH ROOF |
| . PER FBC RES. |
| P3102.1 REQUIRED VENT EXTENSION. |
| THE VENT SYSTEM SERVING EACH BUILDING DRAIN SHALL HAVE |
| AT LEAST ONE VENT PIPE THAT EXTENDS TO THE OUTDOORS. |
| |
| 4. PROVIDE CLEAN OUT OUT SIDE BUILDING PER FBC RES. |
| P3005.2.7 BUILDING DRAIN AND BUILDING SEWER JUNCTION. |
| THERE SHALL BE A CLEANOUT NEAR THE JUNCTION OF THE |
| BUILDING DRAIN AND BUILDING SEWER. THIS CLEANOUT SHALL |
| BE EITHER INSIDE OR OUTSIDE THE BUILDING WALL, PROVIDED |
| THAT IT IS BROUGHT UP TO FINISH GRADE OR TO THE LOWEST |
| FLOOR LEVEL. AN APPROVED TWO-WAY CLEANOUT SHALL BE |
| PERMITTED TO SERVE AS THE REQUIRED CLEANOUT FOR BOTH |
| THE BUILDING DRAIN AND THE BUILDING SEWER. THE CLEANOUT |
| AT THE JUNCTION OF THE BUILDING DRAIN AND BUILDING |
| SEWER SHALL NOT BE REQUIRED WHERE A CLEANOUT ON A |
| 3-INCH (76 MM) OR LARGER DIAMETER SOIL STACK IS LOCATED |
| WITHIN A DEVELOPED LENGTH OF 10 FEET (3048 MM) OF THE |
| BUILDING DRAIN AND BUILDING SEWER JUNCTION. |
| |
| 5. SHOW LOCATION OF RELOCATED TANKLESS WATER HEATER ON |
| ELEVATION DRAWING AND FLOOR PLAN TO SHOW COMPLIANCE |
| WITH CLEARANCE TO OPENINGS IN MANUFACTURE INSTALLATION |
| GUIDE. PER WPB AMEND.TO FBC 107.2.1 |
| |
| |
| |