2016-07-22 15:26:05 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, |
| FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: |
| |
| PLEASE CONSIDER THE FOLLOWING AS PROVISO: |
| |
| THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED |
| AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE |
| PROVISO COMMENTS WILL RESULT IN A FAILED FIRE |
| INSPECTION. |
| |
| 1) SHEET A2 - PER NFPA 101, CHAPTER 43 BUILDING |
| REHABILITATION |
| |
| |
| 43.4 RENOVATIONS. |
| 43.4.1 GENERAL REQUIREMENTS. |
| 43.4.1.3 ALL NEW WORK SHALL COMPLY WITH THE |
| REQUIREMENTS OF THIS CODE APPLICABLE TO EXISTING |
| BUILDINGS. |
| 43.4.1.4 THE WORK SHALL NOT MAKE THE BUILDING LESS |
| CONFORMING WITH OTHER SECTIONS OF THIS CODE, OR WITH |
| ANY PREVIOUS APPROVED ALTERNATIVE ARRANGEMENTS, THAN IT |
| WAS BEFORE THE RENOVATION WAS UNDERTAKEN, UNLESS |
| OTHERWISE SPECIFIED IN 43.4.1.5. |
| |
| ANY REMOVAL AND/OR CONSTRUCTION OF WALLS AND /OR |
| CEILINGS REQUIRE AN EVALUATION OF THE FIRE ALARM AND |
| SPRINKLER SYSTEM FOR CODE COVERAGE AND COMPLIANCE BY |
| CERTIFIED LIFE SAFETY CONTRACTORS. |
| THE LIFE SAFETY SYSTEMS, FIRE ALARM AND/OR FIRE |
| SPRINKLER SHALL REMAIN ACTIVE THROUGHOUT THE |
| CONSTRUCTION PERIOD. |
| ANY AND ALL WORK ON THE FIRE ALARM AND FIRE SPRINKLER |
| SYSTEMS SHALL BE DONE UNDER SEPARATE SHOP DRAWINGS AND |
| BY CERTIFIED LIFE SAFETY CONTRACTORS. |
| ANY TIME THAT WORK ON THE LIFE SAFETY SYSTEMS, |
| SPRINKLER AND/OR FIRE ALARM, EXCEEDS 4 HOURS, A FIRE |
| WATCH SHALL BE IMPLEMENTED AND MAINTAINED UNTIL FULL |
| AND COMPLETE PROTECTION IS RETURNED. |
| |
| 2) THE FIRE INSPECTOR WILL REVIEW AND VERIFY COMPLAINCE |
| NOTED ABOVE. PLEASE ENSURE REVIEW AND COMPLAINCE PRIOR |
| TO INSPECTION. |
| |
| |
| |
| PETER LEDUC |
| FIRE MARSHAL |
| 561-804-4709 |
| [email protected] |
| |