Date |
Text |
2018-06-05 15:21:37 | RESIDENTIAL (R3) REVISION, 8TH BUILDING REVIEW |
| CHECKLIST. |
| CODE: 2010 FBC. |
| |
| ORIGINAL COMMENT: |
| 1- GAF FLAT ROOF NOA 13-1022.15 SPECIFIED ON DRAWING |
| S-2 AND SELECTED INSULATED ASSEMBLY ON PAGE 6 OF 16: |
| PROVIDE SIGNED AND SEALED RAS 117 CALCULATIONS AS |
| REQUIRED BY GENERAL LIMITATION #7 TO MEET THE DESIGN |
| PRESSURES OF SEC. R301.1 AT PERIMETER AND CORNER AREAS. |
| FBC-RESIDENTIAL 2010. |
| NOTE: SEE GENERAL LIMITATION #7 ON LAST PAGE OF NOA |
| SUBMITTED FOR RAS 117 CALCULATIONS REQUIREMENTS. |
| |
| RESPONSE: |
| A) INFORMATION IN RAS 117 CALCULATIONS SUBMITTED DON'T |
| MATCH ENGINEER OF RECORD DRAWINGS SUBMITTED UNDER |
| REVISION #16061282. ENGINEER SELECTED ASSEMBLY WITH THE |
| MAXIMUM DESIGN PRESSURES OF -52.5 . ENGINEER DOING THE |
| RAS 117 CALCULATIONS IS USING ASSEMBLY WITH A MAXIMUM |
| DESIGN PRESSURE OF -45PSF. IN ADDITION, THE FASTENER |
| USED FOR THE ASSEMBLY WITH A MAXIMUM DESIGN PRESSURE OF |
| -45PSF IS DIFFERENT THAN THE ONE SPECIFIED BY THE |
| ENGINEER DOING THE RAS 117 CALCULATIONS. FASTENERS ON |
| THE APPROVED ASSEMBLIES CAN NOT BE INTERCHANGED. REVISE |
| AS REQUIRED TO MATCH. COORDINATE ALL THE INFORMATION TO |
| AVOID MORE CONFLICTS AND UN-NECESSARY DELAYS. SEC. |
| R301.1 FBC-RESIDENTIAL 2010. |
| |
| B) THIS PROJECT WAS REVIEWED UNDER THE 2010 FBC |
| RESIDENTIAL NOT 2017. REVISE AS REQUIRED. CHAPTER 553 |
| F.S. |
| |
| IF YOU HAVE ANY QUESTIONS, PLEASE CONTACT |
| JULIO GOMEZ |
| COMMERCIAL COMBINATION PLANS EXAMINER |
| DEVELOPMENT SERVICES DEPARTMENT |
| BUILDING DIVISION |
| (561)805-6712 |
| [email protected] |
| |
| |