Date Text
2016-06-06 05:15:451) SHOW THE CORRESPONDING EHD NUMBER OF THE CORRUGATED
 STAINLESS STEEL TUBING FOR EACH PIPE SIZE. WPB
 AMENDMENTS TO FBC SEC.107.2.1.
  
 2) SHOW THE DISTANCE FROM THE POINT OF DELIVERY, (METER
 OR MP REGULATOR) TO THE MOST REMOTE OUTLET IN THE
 BUILDING AND / OR SYSTEM PER THE 2014 FBC-FUEL GAS
 SEC.402.4.1 OR 2014 FBC-RES. SEC. G 2413.3.
  
 3) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 ON THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES.
 SEC. G2413.2. .
  
 4) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS /
 INSTALLATION MANUAL FOR ALL GAS EQUIPMENT TO VERIFY
 COMPLIANCE WITH STANDARDS NFPA 54, NFPA 58, AND
 FBC-2014 FUEL GAS CODE SEC. 402.2, AND 301.3 OR 2014
 FBC-RES. SEC. G2404.3. GAS APPLIANCES SHALL BE LISTED
 AND LABELED. THE INSTALLATION MANUALS FOR ALL GAS
 APPLIANCES / EQUIPMENT SHALL BE ONSITE AT THE TIME OF
 INSPECTION. FGC SEC.305.1, FBC-RES. SEC.G2408.1.
  
 5) SHOW THE PIPE SIZE OF THE PIPE ON THE OUTLET OF THE
 METER.
  
 6) SIZE THE LINE TO THE COOKTOP.
  
 7) SHOW THE DISTANCE FROM THE REGULATORS TO THE
 APPLIANCE AND SIZE THE LINES FROM THE REGULATORS TO THE
 APPLIANCE.
  
 8) SUBMIT COPIES OF THE GAS SIZING TABLES USED TO
 DESIGN THE SYSTEM OR WRITE THE NUMBER OF THE SIZING
 TABLE ON THE PLAN FROM THE 2014 FBC- RES. SEC. G2413.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR