Plan Review Notes
Plan Review Notes For Permit 16051290
Permit Number 16051290
Review Stop M
Sequence Number 2
Notes
Date Text
2016-08-05 10:26:308/5/16
 RE-SUBMITTED PLANS ARE MISSING.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
 2ND REVIEW FBC-2014 MECHANICAL
 PERMIT #16051290
 8/11/16
  
 1) THE ENERGYGAUGESUMMIT SUBMITTAL DOES NOT INCLUDE
 COMPLIANCE DATA FOR THE WATER HEATER OR THE CHILLED
 WATER PIPING AND INSULATION.
  
 2) REFER TO COMMENT #4 FROM THE 1ST REVIEW AND SUBMIT
 MANUFACTURER'S SPECIFICATIONS FOR THE CONVECTION OVEN.
 PROVIDE EXHAUST AS REQUIRED BY SECTION 507.2.2 AND
 TABLE 6-4 ASHRAE 62.1-2010.
  
 3) COMMENT #8 FROM THE 1ST REVIEW STILL EXISTS-
 ENGINEERED DETAILS FOR INSTALLATION OF OACU-1 & 2 NOT
 SHOWN ON THE PLAN, ALTHOUGH STRUCTURAL CALCULATIONS
 HAVE BEEN SUBMITTED FOR REVIEW. THE REQUESTED
 MIAMI-DADE ROOF STAND NOA NOT SUBMITTED.
  
 4) COMMENT #11 FROM THE 1ST REVIEW STILL EXISTS. AS
 PREVIOUSLY REQUESTED PROVIDE THE FLEX DUCT SIZES ON THE
 PLAN, OR RELOCATE THE AIR DISTRIBUTION AND FLEX DUCT
 SCHEDULE TO THE M2.1 PLAN SHEET (MECHANICAL DUCTWORK
 PLAN).
  
 5) PROVIDE SUBMITTALS FOR ALL PIPING INSULATIONS TO BE
 INSTALLED IN THE RETURN PLENUM, AND PLACE A NOTE ON
 M2.1 INDICATING THE AREA ABOVE THE CEILING IS A RETURN
 PLENUM- SEE SECTION 602.
  
 6) M2.1: PROVIDE NOTES OR DETAILS TO INDICATE HOW
 SERVICE ACCESS TO ALL ABOVE CEILING MECHANICAL
 EQUIPMENT WILL BE PROVIDED- SECTION 306.1.
  
 7) M2.1 & A1.0: REFER TO SECTION C403.2.7.3 AND TABLE
 C403.2.7.2 FBC-14 ENERGY CONSERVATION, AND SHOW
 COMPLIANCE FOR THE REQUIRED CONTINOUS AIR BARRIER
 FORMING THE ABOVE CEILING RETURN PLENUM.
  
 CHRISTOPHER L. COLE
 MECHANICAL PLANS EXAMINER
 561-805-6719
 [email protected]
  
  
  
  
  