Date |
Text |
2016-06-10 07:45:44 | 1ST REVIEW: FBC 2014 MECHANICAL |
| PERMIT 16051235 |
| 6/10/16 |
| |
| 1) AN AC SYSTEM, EXHAUST FAN, AND MOTORIZED LOUVER ARE |
| SHOWN ON SHEET D-01-01- THE CHEMICAL FEED SHELTER |
| BUILDING: PLEASE PROVIDE MECHANICAL PLANS INCLUDING: |
| A) AC SYSTEM, EXHAUST FAN, AND LOUVER EQUIPMENT |
| SCHEDULES |
| B) AC LOAD CALCULATIONS |
| C) EXHAUST VENTILATION CALCULATIONS |
| D) SEQUENCE OF OPERATIONS FOR THE AC, FAN, AND LOUVER |
| E) WIIND LOAD ENGINEERING FOR INSTALLATION OF THE FAN |
| AND LOUVER. |
| |
| 2) PROVIDE CLEARANCE DISTANCE MEASUREMENTS FOR THE AIR |
| INTAKE LOUVER AS REQUIRED BY SECTION 401.4, AND INTAKE |
| OPENING PROTECTION DETAILS PER 401.5. SUBMIT A FL. |
| PRODUCT APPROVAL OR MIAMI-DADE NOA FOR THE LOUVER WITH |
| APPROVAL SIGNATURE BY THE DESIGN PROFESSIONAL OF |
| RECORD. |
| |
| 3) PROVIDE CLEARANCE DISTANCE MEASUREMENTS FOR THE FAN |
| DISCHARGE AS REQUIRED BY SECTION 501.3.1, AND OPENING |
| PROTECTION DETAILS PER 501.3.2. SUBMIT A FL. PRODUCT |
| APPROVAL OR MIAMI-DADE NOA FOR THE FAN WITH APPROVAL |
| SIGNATURE BY THE DESIGN PROFESSIONAL OF RECORD. |
| |
| 4) PLEASE REFER TO SECTION 414.1.3 FBC-14 BUILDING AND |
| SUBMIT THE REQUIRED REPORT FOR THE SODIUM HYPOCHLORITE |
| AND ALL OTHER CHEMICALS TO BE STORED ON USED FOR |
| PROCESSING IN THE BUILDING. PLEASE NOTE THAT A |
| HAZARDOUS EXHAUST VENTILATION SYSTEM MAY BE REQUIRED- |
| SEE SECTION 510 FBC-14 MECHANICAL FOR CODE |
| REQUIREMENTS. |
| |
| 5) PROVIDE SUBMITTALS FOR ALL PROCESS PIPING, VALVES, |
| AND FITTINGS WITH SHOP DRAWING APPROVAL SIGNATURES FROM |
| THE DESIGN PROFESSIONAL OF RECORD. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |