Plan Review Notes
Plan Review Notes For Permit 16051208
Permit Number 16051208
Review Stop G
Sequence Number 1
Notes
Date Text
2016-09-13 06:48:04GAS PLAN REVIEW
 A GAS PLAN HAS NOT BEEN INCLUDED IN THIS SUBMITTAL
 PACKAGE. A GAS PLAN REVIEW HAS NOT BEEN PERFORMED AT
 THIS TIME. A SEPARATE GAS PERMIT AND PLANS WILL BE
 REQUIRED FOR A CONTRACTOR TO PERFORM THE RELATED WORK.
 PROVIDE COMPLETE PLANS, APPLIANCE/ EQUIPMENT
 SPECIFICATIONS AND GAS RISER THAT REFLECT THE ENTIRE
 SCOPE OF GAS WORK TO BE DONE. WPB AMEND. TO FBC SEC.
 107.2.1.
  
 GAS APPLIANCES SHALL BE LISTED AND LABELED PER THE
 FBC-R, SEC. G2404.3.
 GAS APPLIANCES SHALL BE LISTED AND LABELED PER FBC-FUEL
 GAS SEC. 301.3.
  
 A SEPARATE PERMIT IS REQUIRED FOR THE GAS INSTALLATION.
  
 GAS PERMIT APPLICATION REQUIREMENTS
  
 EFFECTIVE IMMEDIATELY THE FOLLOWING INFORMATION SHALL
 BE SHOWN ON ALL GAS DRAWINGS SUBMITTED FOR PERMITTING
 IN THE CITY OF WEST PALM BEACH:
  
 1. SUBMIT AN ISOMETRIC DRAWING THAT CLEARLY SHOWS ALL
 CUT SECTIONS OF PIPE AND CORRESPONDING LENGTHS PER
 FBC-2014 FUEL GAS, SECS. 402.4.1, 402.4.2.
  
 2. SHOW TYPE OF PIPING MATERIAL BEING INSTALLED, ALL
 PIPE SIZES, AND THE EHD NUMBER OF CORRUGATED STAINLESS
 STEEL TUBING FOR EACH PIPE SIZE IF BEING USED. WPB
 AMENDMENTS TO FBC SEC. 107.2.1.
  
 3. TYPE OF GAS, (LP OR NATURAL).
  
 4. BTU LOAD OF EACH APPLIANCE AND THE TOTAL BTU LOAD ON
 THE SYSTEM. REFER TO THE FBC-2014 FUEL GAS SECS. 401.8
 THRU 402.6.1 AND TABLES 402.4(1) THRU 402.4(37).
  
 5. SHOW THE DISTANCE FROM THE POINT OF DELIVERY,
 (METER), TO THE MOST REMOTE OUTLET IN THE BUILDING
 AND/OR SYSTEM PER THE FBC-2014 FUEL GAS APPENDIX A ?
 USE OF CAPACITY SECTION A.3.1(4) & 2014 FUEL GAS CODE
 SEC. 402.4.1.
  
 6. SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE
 FBC-2014 FUEL GAS CODE SEC. 304.
  
 7. INDICATE THE DELIVERY PRESSURE (PSI) PER FBC-2014
 FUEL GAS SEC. 402.2. IF NATURAL GAS SPECIFY .5 PSI OR 2
 PSI.
  
 8. SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER FBC-2014 FUEL GAS CODE
 SEC. 502 THRU 505.
  
 9. SUBMIT MANUFACTURER?S SPECIFICATION SHEETS FOR ALL
 GAS EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA
 54, NFPA 58, AND FBC-2014 FUEL GAS SEC. 402.2
  
 10. CLEARLY SHOW THE LOCATION AND CAPACITY OF LP
 TANK(S), TYPE OF TANK (DOT OR ASME), THE DISTANCE OF
 THE TANK FROM THE BUILDING AND ADJACENT PROPERTY LINES
 THE DISTANCE OF THE TANK FROM ALL SOURCES OF IGNITION,
 OTHER CONTAINERS, BUILDINGS, AND THE LOCATION OF ANY
 BUILDING OPENINGS BELOW THE RELIEF VALVE OF THE TANK
 PER NFPA 58, TABLE 3-2.2.2.
  
  