2016-08-29 11:52:35 | THIS PLAN WAS REVIEWED AND APPROVED BY PETER LEDUC, |
| FIRE MARSHAL, WITH THE FOLLOWING COMMENTS: |
| |
| PLEASE CONSIDER THE FOLLOWING AS PROVISO: |
| |
| THESE PROVISO COMMENTS WILL BE VERIFIED AND CONFIRMED |
| AT THE TIME OF FIRE INSPECTION. FAILURE TO FOLLOW THESE |
| PROVISO COMMENTS WILL RESULT IN A FAILED FIRE |
| INSPECTION. |
| |
| |
| 1) A NOTE IS INDICATED AS SAYING THAT A PRESSURE TEST |
| IS NOT REQUIRED FOR AREAS THAT CAN NOT BE ISOLATED SUCH |
| AS RELOCATED DROPS. |
| |
| THE CODE REFERNECE INDICATED 24.2.1.6 DOES NOT APPLY. |
| |
| THIS INSTALLATION INDICATES ADDITIONAL BRANCH LINES AND |
| A 200PSI PRESSURE TEST IS REQUIRED. |
| |
| 24.2 ACCEPTANCE REQUIREMENTS. |
| 24.2.1* HYDROSTATIC TESTS. |
| 24.2.1.1 UNLESS PERMITTED BY 24.2.1.2 THROUGH 24.2.1.8, |
| ALL PIPING AND ATTACHED APPURTENANCES SUBJECTED TO |
| SYSTEM WORKING PRESSURE SHALL BE HYDROSTATICALLY TESTED |
| AT 200 PSI (13.8 BAR) AND SHALL MAINTAIN THAT PRESSURE |
| WITHOUT LOSS FOR 2 HOURS. |
| 24.2.1.2 PORTIONS OF SYSTEMS NORMALLY SUBJECTED TO |
| SYSTEM WORKING PRESSURES IN EXCESS OF 150 PSI (10.4 |
| BAR) SHALL BE TESTED AS DESCRIBED IN 24.2.1.1, AT A |
| PRESSURE OF 50 PSI (3.5 BAR) IN EXCESS OF SYSTEM |
| WORKING PRESSURE. |
| 24.2.1.4 MODIFICATIONS AFFECTING 20 OR FEWER SPRINKLERS |
| SHALL NOT REQUIRE TESTING IN EXCESS OF SYSTEM WORKING |
| PRESSURE. |
| 24.2.1.5 WHERE ADDITION OR MODIFICATION IS MADE TO AN |
| EXISTING SYSTEM AFFECTING MORE THAN 20 SPRINKLERS, THE |
| NEW PORTION SHALL BE ISOLATED AND TESTED AT NOT LESS |
| THAN 200 PSI (13.8 BAR) FOR 2 HOURS. |
| 24.2.1.6 MODIFICATIONS THAT CANNOT BE ISOLATED, SUCH AS |
| RELOCATED DROPS, SHALL NOT REQUIRE TESTING IN EXCESS OF |
| SYSTEM WORKING PRESSURE. |
| 24.2.1.7 LOSS SHALL BE DETERMINED BY A DROP IN GAUGE |
| PRESSURE OR VISUAL LEAKAGE. |
| 24.2.1.8* THE TEST PRESSURE SHALL BE READ FROM A GAUGE |
| LOCATED AT THE LOW ELEVATION POINT OF THE SYSTEM OR |
| PORTION BEING TESTED. THE PRESSURES IN PIPING AT HIGHER |
| ELEVATIONS SHALL BE PERMITTED TO BE LESS THAN 200 PSI |
| (13.8 BAR) WHEN ACCOUNTING FOR ELEVATION LOSSES. |
| SYSTEMS OR PORTIONS OF SYSTEMS THAT CAN BE ISOLATED |
| SHALL BE PERMITTED TO BE TESTED SEPARATELY. |
| 24.2.1.9* ADDITIVES, CORROSIVE CHEMICALS SUCH AS SODIUM |
| SILICATE, OR DERIVATIVES OF SODIUM SILICATE, BRINE, OR |
| SIMILAR ACTING CHEMICALS SHALL NOT BE USED WHILE |
| HYDROSTATICALLY TESTING SYSTEMS OR FOR STOPPING LEAKS. |
| 24.2.1.10 PIPING BETWEEN THE EXTERIOR FIRE DEPARTMENT |
| CONNECTION AND THE CHECK VALVE IN THE FIRE DEPARTMENT |
| INLET PIPE SHALL BE HYDROSTATICALLY TESTED IN THE SAME |
| MANNER AS THE BALANCE OF THE SYSTEM. AFTER REPAIR OR |
| REPLACEMENT WORK AFFECTING THE FIRE DEPARTMENT |
| CONNECTION, THE PIPING BETWEEN THE EXTERIOR AND THE |
| CHECK VALVE IN THE FIRE DEPARTMENT INLET PIPE SHALL BE |
| ISOLATED AND HYDROSTATICALLY TESTED AT 150 PSI (10.3 |
| BAR). |
| 24.2.1.11 WHEN SYSTEMS ARE BEING HYDROSTATICALLY |
| TESTED, IT SHALL BE PERMITTED TO CONDUCT TEST WITH |
| PENDENT SPRINKLERS OR PLUGS INSTALLED IN FITTINGS. ANY |
| PLUGS SHALL BE REPLACED WITH PENDENT SPRINKLERS AFTER |
| THE TEST IS COMPLETED. |
| 24.2.1.12 WHEN DELUGE SYSTEMS ARE BEING HYDROSTATICALLY |
| TESTED, PLUGS SHALL BE INSTALLED IN FITTINGS AND |
| REPLACED WITH OPEN SPRINKLERS AFTER THE TEST IS |
| COMPLETED, OR THE OPERATING ELEMENTS OF AUTOMATIC |
| SPRINKLERS SHALL BE REMOVED AFTER THE TEST IS |
| COMPLETED. |
| 24.2.1.13 PROVISION SHALL BE MADE FOR THE PROPER |
| DISPOSAL OF WATER USED FOR FLUSHING OR TESTING. |
| |
| |
| PETER LEDUC |
| FIRE MARSHAL |
| 561-804-4709 |
| [email protected] |
| |