Plan Review Notes
Plan Review Notes For Permit 16051078
Permit Number 16051078
Review Stop G
Sequence Number 2
Notes
Date Text
2016-10-15 08:51:161) SHT. P5.1 - SHOW THE TYPE OF PIPE MATERIAL BEING
 INSTALLED, ALL PIPE SIZES, SIZE THE BRANCH LINES FOR
 GWH-2 & GWH-3. WPB AMENDMENTS TO FBC SEC.107.2.1.
  
 2) INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM
 FROM THE TANK TO THE STEP DOWN REGULATOR AND FROM THE
 STEP DOWN REGULATOR TO THE APPLIANCES. ON THE PLAN PER
 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. SEC. G2413.2.
 . 2ND REQUEST.
  
 3) SUBMIT CALCULATIONS FOR COMBUSTION AIR FOR THE DRYER
 PER 2014 FGC SEC.304.1. 2ND REQUEST. WHAT HAS BEEN
 SUBMITTED IS NON-COMPLIANT AND IS NOT A CALCULATION FOR
 COMBUSTION AIR.THE NOTE AT THE BOTTOM OF THE COMBUSTION
 AIR CALCULATION REFERS TO THE 2010/2009 FLORIDA
 BUILDING CODE. THE CODE IN EFFECT IS THE 2014 CODE.
  
 4) GAS APPLIANNCES SHALL BE LISTED AND LABELED. THE
 INSTALLATION MANUALS FOR ALL GAS APPLIANCES / EQUIPMENT
 SHALL BE ONSITE AT THE TIME OF INSPECTION. FGC
 SEC.305.1. THIS IS FOR INFORMATION ONLY.
  
 5) SHT. C4.01 SHOWS A 1 1/2 INCH GAS LINE AND SHT. P5.1
 SHOWS 2 INCH. CLARIFY. 2ND REQUEST.
  
 6) THE GAS SIZING TABLE REFERENCED ON THE GAS RISER IS
 FOR NATURAL GAS AND THIS SYSTEM IS PROPANE THEREFORE A
 COMPRHENSIVE GAS REVIEW COULD NOT BE DONE. PLACE A
 REFERENCE ON THE PLAN TO THE CORRECT SIZING TABLE USED
 FOR THIS SYSTEM.
  
 7) THE GAS RISER SHOWS THE DRYER AS HAVING 35,000 BTU'S
 AND SHT. P0.1 SHOWS 110,000 BTU'S. CLARIFY.
  
 7) EMERGENCY HOOD SHUT DOWN SHUT OFF VALVE SHALL BE
 BELOW THE CEILING. THE MANUAL SHUTOFF VALVE SHALL BE
 UPSTREAM. UNION TO BE DOWN STREAM OF MANUAL VALVE. SHOW
 THIS ON THE GAS RISER. WPB AMEND. TO FBC SEC. 107.2.1.
  
 8) CLEARLY SHOW THE CAPACITY OF THE LP TANK, TYPE OF
 TANK ( DOT OR ASME ), THE DISTANCE OF THE TANK FROM ALL
 SOURCES OF IGNITION, AND THE LOCATION OF ANY BUILDING
 OPENINGS BELOW THE RELIEF VALVE OF THE TANK. COMPLY
 WITH NFPA 58, TABLE 6.3.1, TABLE 6.3.8, & SECS. 6.3.8 &
 6.3..9.
  
 9) CLEARLY SHOW THE METHOD OF REQUIRED PROTECTION FOR
 THE ABOVEGROUND LP TANK AND APPURTENANCES PER NFPA 58.
 WIND LOAD ANCHORING DETAILS FOR LP TANK BY ENGINEER OF
 RECORD SHALL BE SUBMITTED AT TIME OF LP GAS PERMIT
 APPLICATION.
  
 10) SHT. P5.1 - THE GAS RISER SHOWS THE PRESSURE
 REDUCING FROM 2 PSI TO 0.5 PSI WITHOUT ANY STEP DOWN
 REGULATORS ON THE SYSTEM. SHOW THE LOCATION OF ALL
 STEP-DOWN REGULATORS ON THE RISER.
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]
  
  
  
  
  
  
  