Date |
Text |
2016-05-31 12:36:32 | 1ST REVIEW: FBC 2014 MECHANICAL |
| PERMIT #16051078 |
| 5/30/16 |
| |
| 1) PROVIDE AN EXHAUST VENTILATION SYSTEM FOR THE |
| APPARATUS BAY (ENCLOSED GARAGE) IN COMPLIANCE WITH |
| SECTION 404 FBC-14 MECHANICAL. PLEASE INCLUDE |
| CALCULATIONS, SYSTEM DETAILS, EQUIPMENT SCHEDULES ETC, |
| AND SHOW COMPLIANCE WITH SECTION 404.2 FOR MINIMUM |
| VENTILATION AIRFLOW RATE, AND 404.3 FOR POSITIVE |
| PRESSURE REQUIRMENT FOR ALL ADJOINING SPACES. |
| |
| 2) PROVIDE EXHAUST VENTILATION CALCULATIONS FOR THE |
| BUNKER GEAR ROOM, THE LOCKER ROOM, THE GENERATOR ROOM, |
| THE DECON ROOM, THE JANITOR'S ROOM, AND THE BATHROOMS |
| AND TOILET ROOMS, AND THE SUPPLY STORAGE ROOM PER TABLE |
| 403.3 AND ASHRAE 62.1- 2010. INCLUDE THE SQUARE FOOTAGE |
| OF THE AREAS, THE REQUIRED AND PROVIDED EXHAUST RATES. |
| PLEASE NOTE THE FOLLOWING: A) THE EXHAUST FROM THE |
| BUNKER (LOCKER) ROOM AND THE SUPPLY STORAGE ROOM SHALL |
| DISCHARGE TO THE OUTDOORS - SECTION 501.3. B) THE AIR |
| FROM THE SUPPLY STORAGE ROOM SHALL NOT BE RECIRCULATED |
| INTO THE DECON ROOM AS SHOWN ON SHEET M2.1- SEE SECTION |
| 403.2.1. |
| |
| 3) LABEL THE ERV AT ALL OARTU LOCATIONS SHOWN ON THE |
| PLAN. PLEASE NOTE THAT THE EXHAUST CALCULATIONS SHALL |
| BEAR OUT THAT NOT MORE THEN 10% OF THE EXHAUST AIR FROM |
| THE ROOMS AND SPACES IS BEING RECIRCULATED IN |
| ACCORDANCE WITH TABLE 403.3 FOOTNOTE G. PLEASE SUBMIT |
| DOCUMENTATION FROM THE ERV MANUFACTURER THAT INDICATES |
| THE LEAKAGE RATE OF THE UNIT. |
| |
| 4) REFER TO SECTION 414.1.3 FBC-14 BUILDING AND PROVIDE |
| A LIST OF MATERIALS AND GASES AND THEIR QUANTITIES BE |
| STORED IN THE SUPPLY STORAGE ROOM. |
| |
| 5) SHEET M6.1: THE O/A CALCULATIONS SHOWN IN THE |
| SCHEDULE FOR THE DINING ROOM, GYM ROOM, AND MEDICAL |
| STORAGE ARE LESS THAN THE REQUIRED AMOUNT INDICATED IN |
| TABLE 403.3- PLEASE CORRECT. |
| |
| 6) PROVIDE AIR BALANCE CALCULATIONS THAT INCLUDE ALL |
| THE OUTSIDE AIR AND EXHAUST CFM'S INCLUDING THE KITCHEN |
| EXHAUST SYTEM. |
| |
| 7) M2.1: SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| DRYER, AND PROVIDE EXHAUST DUCT RUN DETAILS- TYPE AND |
| SIZE OF DUCTS, AND TOTAL RUN. |
| |
| 8) M2.1: INDICATE THE SIZES OF THE MAIN TRUNKS DROPPING |
| INTO THE FIRST FLOOR FROM THE SECOND. |
| |
| 9) M2.1 & M2.2: SHOW ALL FLEX DUCT SIZES. |
| |
| 10) M6.1: THE ERV SCHEDULE INDICATES THE UNIT IS TO BE |
| LOCATED IN THE CEILING, BUT ALSO ON THE ROOF ON A CURB- |
| PLEASE CLARIFY. |
| |
| 11) PROVIDE TYPICAL CONNECTIONS AND SUPPORT DETAILS FOR |
| THE DUCTS, EXHAUST FANS, AND THE MMU'S. |
| |
| 12) M2.4: THE OUTDOOR UNITS APPEAR TO HAVE TWO |
| DIFFERENT MODEL NUMBERS: MAP0964HT9UL ON THE DIAGRAM, |
| AND MMY-AP1924HT9UL IN THE SCHEDULE. PLEASE INDICATE |
| THE TYPE OF REFRIGERANT TO BE USED IN THE SYSTEMS AND |
| QUANTITIES PER INDIVIDUAL CIRCUIT. |
| |
| 13) SHOW WHERE ACCESS PANELS WILL BE REQUIRED FOR THE |
| MMU-S AND ALL SERVICEABLE EQUIPMENT BEING LOCATED ABOVE |
| HARD CEILINGS- SECTION 306.1 |
| |
| 14) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE GAS |
| WATER HEATER AND COMBUSTION AIR DUCTS IN THE JANITOR'S |
| ROOM. |
| |
| 15) REFER TO SECTION C403.2.4.4 FBC-14 ENERGY |
| CONSERVATION AND PROVIDE DAMPERS AND SHUTOFF CONTROLS |
| FOR THE EXHAUST DUCTS. |
| |
| 16) THE CU-1 & CU-2 SYSTEMS AND MMU-S ARE NOT INCLUDED |
| IO THE ENERGY CALCULATIONS. |
| |
| 17) REFER TO SECTION 309.1 AND THE SUBMITTED AC |
| CALCULATIONS AND PROVIDE HEAT FOR ALL OCCUPIED ROOMS |
| AND SPACES BEING SERVED BY THE MMU-S: PLEASE NOTE THE |
| EQUIPMENT SCHEDULE DOES NOT INDICATE FACTORY SUPPLIED |
| HEAT FOR THE SYSTEMS. |
| |
| 18) SEPARATE PERMITS ARE REQUIIRED FOR THE KITCHEN HOOD |
| EXHAUST, FIRE SUPPRESSION FOR THE HOOD, AND THE |
| GENERATOR- PLEASE PLACE NOTES ON THE PLAN ACCORDINGLY. |
| |
| 19) THE SUBMITTED PLANS AND STRUCTURAL CALCULATIONS DO |
| NOT INCLUDE CALCULATIONS AND DETAILS FOR ANCHORING THE |
| ROOFTOP AND GOUND-MOUNTED AC EQUIPMENT AND FANS- SEE |
| SECTION 301.15 AND SHOW COMPLIANCE. |
| |
| 20) PROVIDE A SYMBOL ON THE PLANS IDENTIFYING THE |
| LOCATION OF THE REQUIRED DUCT SMOKE DETECTOR IN THE |
| RETURN AIR DUCT OF THE OARTU- SECTION 606.2.1 |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |