Date |
Text |
2016-08-16 08:11:36 | ****CORRECTIONS**** |
| REVISED 9/7 (ITEM 34) |
| |
| SAMANTHA HILL |
| BUILDING PLANS EXAMINER |
| [email protected] |
| 561-805-6724 |
| |
| GOVERNING CODE: FBC 5TH EDITION (FBC 2014) |
| |
| 1. FLORIDA STATUTE 553.71, IT APPEARS THAT THIS |
| BUILDING MAY QUALIFY AS A THRESHOLD BUILDING; ANY |
| BUILDING WHICH IS GREATER THAN (3) STORIES OR 50 FT. IN |
| HEIGHT, OR WHICH HAS AN ASSEMBLY OCCUPANCY |
| CLASSIFICATION AS DEFINED IN THE FLORIDA BUILDING CODE |
| WHICH EXCEEDS 5,000 SF IN AREA AND AN OCCUPANT CONTENT |
| OF GREATER THAN 500 PERSONS. |
| |
| 2. AS A THRESHOLD BUILDING, THE FOLLOWING IS REQUIRED: |
| |
| A. THRESHOLD INSPECTION PLAN; FS 553.79(5)(A), CITY OF |
| WEST PALM BEACH AMENDMENTS TO THE FLORIDA BUILDING |
| CODE, CHAPTER 1, ADMINISTRATION 109.3.6.1. THE |
| ENFORCING AGENCY SHALL REQUIRE A SPECIAL INSPECTOR TO |
| PERFORM STRUCTURAL INSPECTIONS ON A THRESHOLD BUILDING |
| PURSUANT TO A STRUCTURAL INSPECTION PLAN PREPARED BY |
| THE ENGINEER OR ARCHITECT OF RECORD. THE STRUCTURAL |
| INSPECTION PLAN MUST BE SUBMITTED TO AND APPROVED BY |
| THE ENFORCING AGENCY BEFORE THE ISSUANCE OF A BUILDING |
| PERMIT FOR THE CONSTRUCTION OF A THRESHOLD BUILDING. |
| THE PURPOSE OF THE STRUCTURAL INSPECTION PLAN IS TO |
| PROVIDE SPECIFIC INSPECTION PROCEDURES AND SCHEDULES SO |
| THAT THE BUILDING CAN BE ADEQUATELY INSPECTED FOR |
| COMPLIANCE WITH THE PERMITTED DOCUMENTS. |
| |
| B. THRESHOLD INSPECTOR: WPB AMENDMENT 109.3.6.2 W.P.B. |
| CONSTRUCTION SERVICES DEPARTMENT REQUESTS FOR THRESHOLD |
| BUILDINGS A SPECIAL INSPECTOR AS REQUIRED BY FS |
| 553.79(5)(A) TO THE MINIMUM INSPECTIONS REQUIRED BY |
| THIS CODE. THE THRESHOLD INSPECTION FORMS ARE REQUIRED |
| TO BE FILED OUT BY ALL PARTIES, NOTARIZED AND RETURNED |
| TO THIS OFFICE, REVIEWED AND APPROVED PRIOR TO PERMIT |
| ISSUANCE. CONTACT KEN CONRAD, MANAGER OF THE SPECIAL |
| INSPECTOR PROGRAM, AT 561-805-6666 FOR ADDITIONAL |
| INFORMATION. |
| FORMS WERE SENT TO: [email protected] |
| ON 5/28/16. |
| |
| C. SPECIAL INSPECTOR RESUME': PROVIDE A RESUME' OF |
| INSPECTION EXPERIENCE ON PREVIOUS PROJECTS FOR REVIEW |
| BY THE BUILDING OFFICIAL OR HIS DESIGNEE. AFTER THE |
| RESUME' IS REVIEWED, AN INTERVIEW WILL BE SCHEDULED. |
| UNDER NO CIRCUMSTANCES WILL AN INSPECTOR BE INTERVIEWED |
| FOR WORK WITHOUT FIRST MEETING THE ABOVE CRITERIA. THE |
| RESUME' IS TO BE SUBMITTED TO KEN CONRAD (AND COPY |
| SAMANTHA HILL), 561-805-6666, [email protected], |
| [email protected] |
| |
| ALL PROSPECTIVE INSPECTORS ARE TO BE APPROVED BY THE |
| CHIEF BUILDING INSPECTOR AND ALL ARE REQUIRED TO SIGN |
| THE SPECIAL INSPECTOR AGREEMENT. |
| |
| D. CONTRACTOR RESUME': PROVIDE A JOB SUMMARY OR HISTORY |
| FOR THIS TYPE OF CONSTRUCTION. THIS MAY BE SUBMITTED TO |
| KEN CONRAD, (PLEASE COPY SAMANTHA HILL) VIA E-MAIL |
| ([email protected], [email protected]). |
| |
| E. PERMIT DOCUMENTS: PAPER SUBMITTALS REQUIRE THREE |
| SIGNED AND SEALED (IF APPLICABLE) ORIGINAL SETS OF ALL |
| DOCUMENTS. |
| |
| F. THRESHOLD BLDG., REQUIRED STATEMENT: W.P.B. |
| AMENDMENT 110.3.7.4.4 ALL PLANS FOR THE BUILDING WHICH |
| ARE REQUIRED TO BE SIGNED AND SEALED BY THE ARCHITECT |
| OR ENGINEER OF RECORD CONTAIN A STATEMENT THAT, TO THE |
| BEST OF THE ARCHITECT'S OR ENGINEER'S KNOWLEDGE, THE |
| PLANS AND SPECIFICATIONS COMPLY WITH THE APPLICABLE |
| MINIMUM BUILDING CODES AND THE APPLICABLE FIRESAFETY |
| STANDARDS AS DETERMINED BY THE LOCAL AUTHORITY IN |
| ACCORDANCE WITH THIS CHAPTER AND CHAPTER 633. |
| |
| (ARCHITECT OK - REVISED PLAN) |
| |
| THE ENGINEER HAS A SIMILAR STATEMENT BUT LACKS SOME OF |
| THE STATUTORY LANGUAGE; PLEASE REVISE. |
| |
| 3. ADVISORY ONLY; PER FS 553.79, ALL SHORING/RE-SHORE |
| ENGINEERING IS TO BE REVIEWED BY ENGINEER OF RECORD |
| AND THREE SIGNED AND SEALED ORIGINAL SETS ARE TO BE |
| SUBMITTED FOR PLAN REVIEW. THE SHORING/RESHORE |
| ENGINEERING IS TO BE REVIEWED AND APPROVED PRIOR TO |
| INSPECTION. THE CITY APPROVED (CITY STAMPED) |
| SHORING/RE-SHORE ENGINEERING IS TO BE AVAILABLE ON THE |
| JOB AT THE TIME OF INSPECTION. |
| |
| 4. ADVISORY ONLY; PRIOR TO INSTALLATION, A GUARD RAIL |
| DETAIL IS TO BE SUBMITTED FOR PLAN REVIEW. THIS SHOULD |
| BE SUBMITTED WITH THE SHORING/RESHORE ENGINEERING. |
| |
| 5. SEE IMPACT FEE REVIEW. |
| |
| 6. ADVISORY ONLY; SEE ROOF (R STOP) REVIEW. NO ROOFING |
| INFORMATION PROVIDED IF ROOFING INFORMATION (PRODUCT |
| APPROVAL REVIEWED BY DESIGNER OF RECORD, ASSEMBLY |
| PROPOSED, ENHANCED FASTENING CALCULATIONS IF REQUIRED) |
| IS NOT SUBMITTED PRIOR TO PERMIT ISSUANCE, THIS PERMIT |
| WILL BE ISSUED WITH PROVISO. ROOF INFORMATION WILL BE |
| REQUIRED TO BE SUBMITTED, REVIEWED AND APPROVED PRIOR |
| TO INSTALLATION. |
| |
| 9. THREE COMPLETE SETS OF PLANS REQUIRED FOR ALL |
| THRESHOLD JOBS (CITY, CONTRACTOR, THRESHOLD INSPECTOR). |
| |
| 11 TO 18. OK |
| |
| 19. LS101, ACADEMICS TEAM ROOM OCCUPANT LOAD IS SHOWN |
| AS 20 SF PER PERSON, CLARIFY, APPEARS TO BE A TYPO AS |
| THIS SHOULD BE 15 SF (AND OCC LOAD CALCULATED USING 15 |
| SF). REVISE PLAN TO CLARIFY USE OF THE SPACE. 15SF IS |
| FOR AREAS WITH TABLES AND CHAIRS, AREAS WITH CHAIRS |
| ONLY SHOULD USE 7 SF, AND STANDING AREAS SHOULD USE |
| 5SF. |
| |
| 2ND REVIEW, ARCHITECT?S RESPONSE IS ACCEPTABLE. PLEASE |
| REVISE PLAN TO NOTE THAT ACADEMICS TEAM ROOM IS A |
| CLASSROOM, ACCESSORY USE. |
| |
| 20. LS101, THE ACADEMICS TEAM ROOM MEANS OF EGRESS |
| FORCES THE OCCUPANT TO TRAVEL THROUGH A SPACE WHICH IS |
| A WORK AREA, WHICH APPEARS TO BE PROHIBITED BY FBC |
| 1014.2. REVISE PLAN TO EITHER MODIFY EXITING STRATEGY |
| OR REVISE PLAN TO SHOW COMPLIANCE (I.E., SHOW HOW THE |
| TWO SPACES ARE ACCESSORY TO ONE ANOTHER). |
| |
| 2ND REVIEW, RESPONSE STATES THAT DIRECT ACCESS TO THE |
| CORRIDOR WAS PROVIDED. PLEASE SEE LS101; THE NEW ACCESS |
| TO CORRIDOR APPEARS TO BE LABELED STORAGE ON ALL |
| SHEETS. PLEASE REVISE THE LIFE SAFETY AND FLOOR PLAN. |
| IT APPEARS THAT THE STORAGE ROOM MAY BE THE ADJACENT |
| ROOM. ALSO PLEASE INCLUDE THE DIMENSION BETWEEN THE TWO |
| DOORS TO SHOW COMPLIANCE WITH FBC 5TH EDITION |
| ACCESSIBILITY FIGURE 404.2.6. |
| |
| 24 - 27. OK |
| |
| 30. OK |
| |
| 31 TO 33. OK |
| |
| 34. REVISED 9/7 - RECEIVED LETTER FROM ENGINEER |
| REGARDING RATIONALE FOR RISK CATEGORY II. LETTER IS |
| ACCEPTABLE; PLEASE INCLUDE THE SIGNED, SEALED ORGINAL |
| WITH THE RESUBMITTAL. |
| |
| 35. OK |
| |
| 36. FBC 1008.1.10, REVISE DOOR SCHEDULE AE701 TO |
| INCLUDE DOOR HARDWARE; IT IS NOT CLEAR WHERE PANIC |
| HARDWARE IS PROPOSED. |
| |
| FBC TABLE 716.5, EXIT ENCLOSURES REQUIRE 1 HOUR DOORS; |
| DOOR 101 PROPOSES 20 MIN, PLEASE REVISE. |
| |
| ALSO, REGARDING THIS EXIT STAIR WHICH DISCHARGES INTO |
| THE FIRST FLOOR, SEE FBC 1027.1 EXCEPTION 1.1, THE EXIT |
| IS TO BE READILY VISIBLE AND IDENTIFIABLE FROM THE |
| POINT OF TERMINATION OF THE ENCLOSURE. PLEASE SEE |
| CLARIFICATION IN THE COMMENTARY, WHICH SPECIFICALLY |
| STATES THAT THE OCCUPANT SHOULD NOT BE REQUIRED TO TURN |
| COMPLETELY AROUND OR AROUND A CORNER. IT APPEARS THAT |
| EITHER THE DOOR SHOULD OPEN DIRECTLY INTO THE DIRECTION |
| OF THE EXIT DISCHARGE OR THE WALL AT THE END OF THE |
| FIRST FLOOR STAIR SHOULD BE RATED THE SAME AS THE STAIR |
| IF THIS IS TO BE CONSIDERED A CONTINUATION OF THE STAIR |
| EXIT. |
| |
| 37. FROM PREVIOUS LIST: A SPOT CHECK OF THE ENERGY |
| CALCS WAS DONE; PLEASE CLARIFY THE FOLLOWING OR REVISE |
| PLAN: |
| ROOF INSULATION IS R20 ON ENERGY CALCS, R19 ON PLAN |
| |
| 2ND REVIEW, THIS WAS CORRECTED BUT STILL SPECS R19 IN |
| SOME LOCATIONS (SEE AE320, AE321). PLEASE REVISE AND |
| CHECK ALL. |
| |
| 38. THIS PERMIT WILL BE ISSUED WITH THE FOLLOWING |
| PROVISOS: |
| |
| COMPONENTS AND CLADDING PRODUCT APPROVALS REVIEWED BY |
| DESIGNER OF RECORD ARE TO BE SUBMITTED, REVIEWED AND |
| APPROVED PRIOR TO INSTALLATION |
| |
| SEPARATE PERMITS, PLANS, REVIEWS, AND FEES WILL BE |
| REQUIRED FOR SIGNS, AWNINGS, PARKING |
| |
| NEW COMMENT: |
| |
| 39. PLAN REVIEW NOTE: THIS PLAN WAS RESUBMITTED PRIOR |
| TO BUILDING PLAN REVIEW #2. |
| |
| PLEASE SEE FS553.80 (NOTE LANGUAGE "SHALL IMPOSE" |
| RATHER THAN "MAY"): |
| (B)"WITH RESPECT TO EVALUATION OF DESIGN PROFESSIONALS' |
| DOCUMENTS, IF A LOCAL GOVERNMENT FINDS IT NECESSARY, IN |
| ORDER TO ENFORCE COMPLIANCE WITH THE FLORIDA BUILDING |
| CODE AND ISSUE A PERMIT, TO REJECT DESIGN DOCUMENTS |
| REQUIRED BY THE CODE THREE OR MORE TIMES FOR FAILURE TO |
| CORRECT A CODE VIOLATION SPECIFICALLY AND CONTINUOUSLY |
| NOTED IN EACH REJECTION, INCLUDING, BUT NOT LIMITED TO, |
| EGRESS, FIRE PROTECTION, STRUCTURAL STABILITY, ENERGY, |
| ACCESSIBILITY, LIGHTING, VENTILATION, ELECTRICAL, |
| MECHANICAL, PLUMBING, AND GAS SYSTEMS, OR OTHER |
| REQUIREMENTS IDENTIFIED BY RULE OF THE FLORIDA BUILDING |
| COMMISSION ADOPTED PURSUANT TO CHAPTER 120, THE LOCAL |
| GOVERNMENT SHALL IMPOSE, EACH TIME AFTER THE THIRD SUCH |
| REVIEW THE PLANS ARE REJECTED FOR THAT CODE VIOLATION, |
| A FEE OF FOUR TIMES THE AMOUNT OF THE PROPORTION OF THE |
| PERMIT FEE ATTRIBUTED TO PLANS REVIEW. |
| |
| FOR THIS PROJECT, PLAN REVIEW FEE IS $22,637 (4X FEE = |
| $90,548). IF DESIGN PROFESSIONAL DISAGREES WITH A |
| SIGNIFICANT PLAN REVIEW COMMENT FOR ANY PROJECT, IT IS |
| RESPECTFULLY SUGGESTED THAT THE APPROPRIATE REVIEWER BE |
| CONTACTED AND RESOLVE PRIOR TO RESUBMITTING. ALTHOUGH |
| LANGUAGE REQUIRES THAT THE FEE BE IMPOSED, IT IS NOT |
| BEING IMPOSED AT THIS TIME DUE TO THE FACT THAT SINCE |
| PLANS WERE RESUBMITTED WITHOUT ADDRESSING BUILDING |
| COMMENTS FROM REVIEW 1, THIS IS BUILDING REVIEW 2 |
| RATHER THAN BUILDING REVIEW 3. PLEASE ALLOW ALL TRADES |
| TO COMPLETE REVIEWS PRIOR TO RESUBMITTAL. |
| |