Date |
Text |
2016-06-01 08:50:51 | PROVISOS: |
| |
| 1. CIVIL PLANS ARE UNDER REVIEW THRU ENGINEERING |
| SERVICES, A SEPARATE PERMIT IS REQUIRED FOR FIRELINE |
| ON-SITE. |
| THIS SHALL INCLUDE SUBMISSION OF CIVIL PLANS SHEET C-1 |
| THRU C-9 TO OBTAIN A UG FIRELINE, FA OR FS PERMIT. |
| INCLUDE ON PLANS THE FIRE HYDRANT PRESSURE TEST, TIME, |
| LOCATION, WHO PERFORMED THE TEST AND RESULTS. |
| |
| 2. CIVIL PLANS REQUIRE PALM BEACH COUNTY HEALTH |
| DEPARTMENT REVIEW AND APPROVAL. |
| |
| 3. A RIGHT-OF-WAY PERMIT THRU ENGINEERING WILL ALSO BE |
| REQUIRED FOR CITY UTILITY WORK. |
| |
| 4. CONTRACTOR SHALL USE THE CITY'S ENGINEERING STANDARD |
| DETAILS AVAILABLE. |
| HTTP://WPBFL.US/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FO |
| RMS,-PERMITS-APPLICATIONS |
| INCLUDING "PRESSURE PIPE" SERIES. |
| |
| 5. A PRE-CONSTRUCTION MEETING WILL BE REQUIRED WITH THE |
| CITY OF WPB ENGIEERING DEPARTMENT PRIOR TO ANY PUBLIC |
| UTILITY EXCAVATIONS. |
| |
| 6. SEC. 90-203. - PROHIBITED DISCHARGES; ILLICIT |
| CONNECTIONS. |
| (A) GENERAL PROHIBITION. EXCEPT AS PROVIDED IN SECTION |
| 90-205, AND EXCEPT PURSUANT TO A VALID NPDES PERMIT, IT |
| SHALL BE UNLAWFUL FOR ANY PERSON TO DIRECTLY OR |
| INDIRECTLY DEPOSIT, DISCHARGE, SPILL, OR DUMP INTO ANY |
| OF THE PUBLIC WATERS OR MUNICIPAL SEPARATE STORM SEWER |
| SYSTEM WITHIN THE CITY, ANY SUBSTANCE OTHER THAN THAT |
| COMPOSED ENTIRELY OF STORMWATER. |
| (B) SITE OF INDUSTRIAL ACTIVITY. EXCEPT AS PROVIDED IN |
| SECTION 90-205, ANY DIRECT OR INDIRECT DISCHARGE FROM A |
| SITE OF INDUSTRIAL ACTIVITY TO THE SEPARATE STORM SEWER |
| SYSTEM OWNED BY THE CITY WHICH DOES NOT COMPLY WITH, OR |
| IS NOT PURSUANT TO, A VALID NPDES PERMIT IS PROHIBITED. |
| (C) ILLICIT CONNECTIONS. NO PERSON MAY MAINTAIN, USE OR |
| ESTABLISH ANY DIRECT OR INDIRECT CONNECTION TO THE |
| STORMWATER SYSTEM THAT RESULTS IN ANY DISCHARGE IN |
| VIOLATION OF THIS ARTICLE. THIS PROHIBITION IS |
| RETROACTIVE AND APPLIES TO CONNECTIONS MADE IN THE |
| PAST, REGARDLESS OF WHETHER MADE UNDER A PERMIT, OR |
| OTHER AUTHORIZATION, OR WHETHER PERMISSIBLE UNDER LAWS |
| OR PRACTICES APPLICABLE OR PREVAILING AT THE TIME THE |
| CONNECTION WAS MADE. (CODE 1979, 32-18) |
| |
| 7. NOTIFY - PERVIOUS AND IMPERVIOUS AREAS CALCULATIONS |
| TO CITY OF WEST PALM BEACH ENGINEERING DEPARTMENT. |
| |
| 8. ANY SIDEWALKS OR ADA PATHS NEAR AND ALONG THE |
| PERIMETER OF THE PROPERTY SHALL CONFORM TO ADAAG |
| STANDARDS FOR MINIMUM SLOPE AND WIDTH ACCESS. |
| |
| 9. ANY EXISTING PUBLIC UTILITY CONNECTION NOT NEEDED |
| FOR USE OF THE DEVELOPMENT SHALL BE CUT AND CAPPED AT |
| THE MAIN. ANY DEVIATION OR HARDSHIP MAY BE EXPRESSED IN |
| WRITING TO THE CITY OF WEST PALM BEACH PUBLIC UTILITY |
| DIRECTOR IN WRITING. PLAN SHOWS WATER AND SEWER |
| SERVICES THAT WILL NOT BE USED. |
| |
| 10. CALL 811 BEFORE DIG, SHALL BE IN ALL UTILITY PLANS. |
| |
| MANUEL JULIAN GONZALEZ |
| ENGINEERING PROJECT COORDINATOR |
| PUBLIC WORKS DEPARTMENT |
| 401 CLEMATIS STREET, 4TH FLOOR |
| WEST PALM BEACH, FL 33401 |
| (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| MAIN PHONE: (561) 822-1200 |
| DIRECT: (561) 494-1085 |
| FAX: (561) 494-1116 |
| EMAIL: [email protected] |