Date |
Text |
2016-04-14 18:43:36 | FAILED 1ST ELECTRICAL REVIEW |
| REVIEWED FOR COMPLIANCE WITH: |
| 5TH EDITION OF THE FBC 2014 & NFPA 70 (NEC) 2011 |
| EDITION |
| |
| CORRECTIONS REQUIRED: |
| 1. GENERAL DEMOLITION NOTES #10 YOU SHALL INDICATE THE |
| ACTUAL CODE BY WHICH THE SYSTEM IS DESIGNED. (2011 |
| EDITION OF THE NEC). |
| 2. IF THE GENERATOR IS PART OF THE SCOPE OF THIS |
| PROJECT, A SEPARATE PERMIT FOR THE GENERATOR WILL BE |
| REQUIRED. YOU SHALL PROVIDE MANUFACTURER SPEC SHEETS |
| FOR THE GENERATOR. |
| 3. YOU SHALL ALSO SUBMIT A SITE PLAN REFLECTING THE |
| PROPOSED LOCATION OF THE GENERATOR. |
| 4. SERVICE RISER DIAGRAM FAILS TO INCLUDE THE REQUIRED |
| GROUNDING DETAIL. PROVIDE SERVICE GROUNDING FOR EACH |
| SERVICE AND CONNECTED THEM AS PER NEC 250.30(6). |
| 5. PROVIDE PLACARDS AND LABELS AS REQUIRED BY THE |
| VARIOUS ARTICLES OF THE NEC: 230.2(E); 110.15; 110.16 |
| AND 110.24. |
| 6. SUBMIT MANUFACTURER SPEC FOR THE ATS. IT SHALL BE |
| SERVICE RATED. |
| 7. IF THE INTENT IS TO PROVIDE A SEPARATELY DERIVED |
| SERVICE FOR THE GENERATOR, THE ATS SHALL BE CAPABLE OF |
| OPENING THE GROUNDED CONDUCTOR, OTHERWISE THE GROUNDING |
| ELECTRODE INDICATED ADJACENT TO THE GENERATOR SHALL BE |
| REMOVED. |
| |
| WHEN RESUBMITTING, FOR A QUICKER RETURN ON YOUR |
| RE-SUBMITTAL, PLEASE PROVIDE A RESPONSE LETTER |
| (NARRATIVE) ADDRESSING EACH ITEM AND THE PAGE NUMBER |
| WHERE THE CORRECTIONS APPEAR ALONG WITH THE STANDARD |
| CITY RE-SUBMITTAL FORM. ADDITIONALLY, PLEASE INSERT |
| CORRECTED PAGES INTO THE SUBMITTAL PACKAGE. MARK VOID |
| AND LEAVE THE PREVIOUSLY REVIEWED SHEETS FOR |
| COMPARATIVE REVIEW. CLOUDING THE CHANGES WILL BE |
| GREATLY APPRECIATED. |
| |
| IF YOU HAVE FURTHER QUESTIONS, PLEASE DON?T HESITATE TO |
| CONTACT ME DIRECTLY. |
| |
| THANK YOU, |
| MIKE ALBARRAN |
| ELECTRICAL PLANS EXAMINER |
| PH: 561-805-6746 |
| EMAIL: [email protected] |
| |
2016-04-13 08:59:39 | WHEN I WENT TO THE BIN, THE FILE WAS NOT THERE. |