2016-07-20 12:14:25 | THIS PLAN WAS REVIEWED AND FAILED BY PETER LEDUC, FIRE |
| MARSHAL, WITH THE FOLLOWING COMMENTS: |
| |
| PROGRESS IS BEING MADE AND ALL EFFORTS ARE APPRECIATED; |
| HOWEVER, LIFE SAFETY CONCERNS REMAIN UNCLEAR. |
| |
| |
| |
| |
| 1) A LIFE SAFETY PLAN, DURING CONSTURCTION IS NEEDED TO |
| ASSIST MY REVIEW OF HOW/WHERE WILL THE RESIDENTS EXIT |
| DURING CONSTRUCTION. |
| |
| IT APPEARS THAT THE HALLWAYS LEADING TO THE SECONDARY |
| EXIT EGRESS, THE FIRE ESCAPE STAIRS, APPEARS TO BE/WILL |
| BE BLOCKED BY CONSTURCTION. |
| |
| PLEASE PROVIDE DETAIL OF HOW EACH FLOOR WIL HAVE SAFE |
| TRAVEL TO TWO REMOTE EXITS DURING CONSTUCTION. |
| |
| |
| 2) DUE TO THE NATURE OF THE DEMOLITION AND AGE OF THE |
| BUILDING I AM CONCERNED REGARDING THE SAFETY OF THE |
| OCCUPANTS DURING CONSTRUCTION, ESPECIALLY DURING THE |
| DEMOLITION, POTENTIALLY UNSTABLE STRUCTURE, PERIOD. |
| |
| THERE IS NO NOTE/NARRATIVE/STATEMENT/RECOMMENDATION OF |
| ANYONE WITH THE EXPERTISE AS TO THE CONTINUED OCCUPANCY |
| OF RESIDENTS OF THE BUILDING DURING THE |
| DEMOLITION/CONSTRUCTION PERIODS. |
| |
| PLEASE PROVIDE SOME SORT OF OFFICIAL SIGNED AND SEALED |
| DOCUMENTATION FROM A QUALIFIED LICENSED AUTHORITY TO |
| CONFIRMED/VERIFY THE RESIDENTS SAFETY OCCUPYING THE |
| BUILDING DURING DEMOLITION/CONSTRUCTION. |
| |
| |
| 3) THERE DOES NOT APPEAR TO BE A NOTE OR NARRATIVE |
| REAGARDING ALL WORK ON THE FIRE LARM OR FIRE SPRINKLER |
| SHALL BE DONE BY CERITIFED LIFE SAFETY CONTRACTORS |
| UNDER SEPARATE SHOP DRAWINGS. |
| |
| PLEASE PROVIDE. |
| |
| |
| 4) THE VALUE OF THIS PROJECT $150,000 APPEARS TO BE TOO |
| LOW, PLEASE PROVIDE VERIFICATION/JUSTIFICATION AND/OR |
| INCREASE ACCORDINGLY. |
| |
| |
| PETER LEDUC |
| FIRE MARSHAL |
| 561-804-4709 |
| [email protected] |
| |