2016-05-11 13:15:07 | ****CORRECTIONS**** |
| |
| SAMANTHA HILL |
| BUILDING PLANS EXAMINER |
| [email protected] |
| 561-805-6724 |
| |
| FROM PREVIOUS LIST: |
| |
| 10. PROVIDE A SITE PLAN WHICH SHOWS THE PROPOSED |
| UNIFIED PARCEL, BUILDING OUTLINE, AND DISTANCE OF THE |
| EXTERIOR WALLS TO THE PROPERTY LINE OR CENTERLINE OF |
| PUBLIC WAY TO SHOW COMPLIANCE WITH FBC TABLE 705.8. |
| |
| 2ND REVIEW, APPLICABLE DIMENSIONS ARE NOT SHOWN. PLEASE |
| REVISE PLAN TO SHOW THE DISTANCE FROM THE PROPOSED |
| BUILDING TO THE PROPERTY LINE OR TO CENTERLINE OF |
| PUBLIC WAY. IF ANY EXCEPTIONS ARE USED, PLEASE NOTE. |
| SEE FBC TABLE 602, 705.8. THE DISTANCE TO PROPERTY LINE |
| (OR CENTERLINE OF PUBLIC WAY) IS NOT CLEAR. THE WIDTH |
| OF THE PUBLIC WAY ON EACH SIDE SHOULD BE SHOWN SO |
| COMPLIANCE IS CLEAR. |
| |
| 11. SEE GEOTECHNICAL REPORT, SECTION 7.2.2, NOTE 18, AN |
| NV5 SHOULD PROVIDE FULL TIME QUALITY CONTROL INSPECTION |
| TO DOCUMENT THE EXCAVATION AND GROUTING OF EACH PILE |
| AND TO PROVIDE, IN CONJUNCTION WITH A LICENSED OFFICE |
| ENGINEER, ANY NECESSARY FIELD ADJUSTMENTS OF PILE TIP |
| ELEVATIONS. DOES APPLICANT INTEND TO ACCEPT THIS |
| RECOMMENDATION? IF NOT, WHAT OTHER PROVISIONS WILL BE |
| MADE FOR QUALITY CONTROL AND TO ADDRESS 2014 FBC-B |
| 1810.3.5.2.2 (SEE COMMENT BELOW). |
| |
| RESPONSE LETTER STATES THAT OWNERSHIP HAS ADVISED THE |
| DESIGN TEAM THEY WILL ADDRESS THIS ISSUE DIRECTLY WITH |
| THE APPROPRIATE BUILDING OFFICIAL. THIS IS TO BE |
| ADDRESSED PRIOR TO ISSUANCE. |
| |
| 12. SEE GEOTECHNICAL REPORT, SECTION 8.0 REGARDING |
| SOILS ENGINEER RECOMMENDATION THAT THEY REVIEW THE |
| FOUNDATION DESIGN; HAS THIS BEEN DONE? PROVIDE A LETTER |
| OR SHOP DRAWING REVIEW STAMP, FBC 107. |
| |
| 13. REGARDING THE WIND TUNNEL TEST, PROVIDE ONE OF THE |
| FOLLOWING: |
| |
| A. ENGINEERING IS TO BE SIGNED AND SEALED BY A FLORIDA |
| REGISTERED PE, FS 471, OR |
| B. ENGINEER OF RECORD IS TO PROVIDE A SHOP DRAWING |
| REVIEW OR A LETTER WHICH STATES THAT HE ACCEPTS THE |
| REPORT'S FINDINGS AND FINDS THAT THE TEST WAS DONE WITH |
| STANDARD ENGINEERING PRACTICE |
| |
| RESPONSE LETTER STATES THAT OWNERSHIP HAS ADVISED THE |
| DESIGN TEAM THEY WILL ADDRESS THIS ISSUE DIRECTLY WITH |
| THE APPROPRIATE BUILDING OFFICIAL. THIS IS TO BE |
| ADDRESSED PRIOR TO ISSUANCE. |
| |
| ***** |
| PLEASE CONTACT ME REGARDING A POSSIBLE PROVISO FOR THE |
| ABOVE ITEMS. |
| ***** |
| |
| THIS PERMIT WILL BE ISSUED WITH THE FOLLOWING PROVISOS: |
| |
| ****PROVISOS**** |
| ****ISSUED AT CONTRACTOR?S RISK**** |
| |
| SAMANTHA HILL |
| BUILDING PLANS EXAMINER |
| [email protected] |
| 561-805-6724 |
| |
| 1. FBC 105.13 PHASED PERMIT APPROVAL. AFTER SUBMITTAL |
| OF THE APPROPRIATE CONSTRUCTION DOCUMENTS, THE BUILDING |
| OFFICIAL IS AUTHORIZED TO ISSUE A PERMIT FOR THE |
| CONSTRUCTION OF FOUNDATIONS OR ANY OTHER PART OF A |
| BUILDING OR STRUCTURE BEFORE THE CONSTRUCTION DOCUMENTS |
| FOR THE WHOLE BUILDING OR STRUCTURE HAVE BEEN |
| SUBMITTED. THE HOLDER OF SUCH PERMIT FOR THE FOUNDATION |
| OR OTHER PARTS OF A BUILDING OR STRUCTURE SHALL PROCEED |
| AT THE HOLDER?S OWN RISK WITH THE BUILDING OPERATION |
| AND WITHOUT ASSURANCE THAT A PERMIT FOR THE ENTIRE |
| STRUCTURE WILL BE GRANTED. CORRECTIONS MAY BE REQUIRED |
| TO MEET THE REQUIREMENTS OF THE TECHNICAL CODES. THIS |
| PROVISION IS ONLY FOR THE FLORIDA BUILDING CODE, ALL |
| OTHER AGENCY APPROVALS NECESSARY FOR CONSTRUCTION MUST |
| BE SECURED PRIOR TO THIS PROVISION BEING APPLIED. |
| |
| 2. A REPLAT IS REQUIRED FOR COMPLIANCE WITH FBC 705.8. |
| WHEN AVAILABLE, PROVIDE THE BOOK AND PAGE WHERE THIS |
| HAS BEEN RECORDED OR PROVIDE A COPY OF THE RECORDED |
| PLAT. |
| |
| |
| |