Plan Review Notes For Permit 16010659 |
Permit Number |
16010659 |
|
Review Stop |
G |
Sequence Number |
1 |
|
Notes |
Date |
Text |
2016-01-28 05:32:59 | 1) SHOW THE BTU LOAD OF EACH APPLIANCE AND THE TOTAL | | BTU LOAD ON THE SYSTEM. IS THE FIREPLACE GAS/ IF SO, | | SHOW IT ON THE GAS PIPING RISER.REFER TO THE 2014 | | FBC-FUEL GAS SECS.401.8 THRU 402.6.1 AND TABLES 402.4 | | (1) THRU 402.4 (37) OR 2014 FBC-RES. SEC. G2413. | | 2)INDICATE THE DELIVERY PRESSURE (PSI) OF THE SYSTEM ON | | THE PLAN PER 2014 FBC-FUEL GAS SEC.402.2 OR FBC RES. | | SEC. G2413.2. | | 3) INDICATE THE GAS APPLIANCE ON THE GAS RISER. | | 4) A SEPARATE PERMIT IS REQUIRED FOR THE GAS SYSTEM. | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | | | |
|