2015-12-16 10:24:48 | 1ST REVIEW 2014 MECHANICAL |
| PERMIT #15110794 |
| 12/16/15 |
| |
| 1) ADVIORY: UNDERGROUND FUEL TANKS AND DELIVERY SYSTEMS |
| EXCEEDING 550 GALLONS MUST BE APPROVED BY THE PALM |
| BEACH COUNTY DEPARTMENT OF ENVIRONEMNETAL RESOURCE |
| MANAGEMENT. PROVIDE DOCUMENTATION OF APPROVAL FOR THE |
| 8000 GALLON DIESEL FUEL TANK INSTALLATION. |
| 2) PROVIDE A SOIL REPORT FROM A FL. LICENSED ENGINEER |
| FOR INSTALLATION OF THE UNDERGROUND TANK AND NEW |
| GENERATOR BUILDING- SEE SECTION 1803 FBC-14 BUILDING. |
| 3) SUBMIT MANUFACTURER'S SPECIFICATIONS FOR THE |
| GENERATOR, FUEL TANK, FUEL PIPING, AND THE GENERATOR |
| EXHAUST FAN APPROVED BY THE ENGINEER OF RECORD. |
| 4) PROVIDE ON THE PLANS THE WIND LOAD DESIGN CRITERIA |
| AS OUTLINED IN SECTION 1609 FBC-14 BUILDING.WIND DESIGN |
| CRITERIA 2010 FBC-B 1609.1.1 DETERMINATION OF WIND |
| DESIGN- CHAPTER 6 OF ASCE 7-10. |
| SECTION 1609.3 BASIC WIND SPEED FIGURE 1609.A-C. |
| SECTION 1609.3 WIND SPEED CONVERSION |
| A) THE BASIC WIND SPEED, VU, SHALL BE DETERMINED IN |
| ACCORDANCE WITH 1609.3.1 & ASCE 7-10 |
| B) AN IMPORTANCE FACTOR, FIGURE 1609 A-C, ASCE 7-10. |
| C) AN EXPOSURE CATEGORY SHALL BE DETERMINED IN |
| ACCORDANCE WITH 1609.4 & ASCE 7-10 |
| D) A HEIGHT AND EXPOSURE ADJUSTMENT COEFFICIENT, * |
| SHALL BE DETERMINED FROM TABLE 1609.7.2. ASCE 7-10. |
| E) COMPONENTS & CLADDING PRESSURES POSITIVE & NEGATIVE |
| TABLE 1609.2(2). |
| F) COMPONENTS AND CLADDING/ 2010 FBC-B 1609.1.2 |
| PROTECTION OF OPENINGS, 1609.6.4.4.1 COMPONENTS & |
| CLADDING |
| FLORIDA DEPARTMENT OF COMMUNITY AFFAIRS RULE 9N-3 NOV. |
| 01/ 2010 (31) SUB-CATEGORY OF PRODUCTS OR CONSTRUCTION |
| SYSTEMS THAT WILL REQUIRE PRODUCT APPROVALS FOR THE |
| MECHANICAL SYSTEMS: THE INTAKE AND EXHAUST LOUVERS, AND |
| ROOF MOUNTED EXHAUST FAN. PLEASE NOTE SITE SPECIFIC |
| ENGINEERING IS REQUIRED FOR ATTACHMENT OF ALL EXTERIOR |
| EQUIPMENT AND APPLIANCES- PROVIDE ATTACHMENT DETAILS. |
| 5) INDICATE WHICH CODE OR STANDARD WAS USED TO |
| CALCULATE AND DESIGN THE EXHAUST SYSTEM FOR THE |
| GENERATOR BUILDING AND SHOW THE VENTILATION |
| CALCULATION. |
| 6) PROVIDE A SECTION VIEW OF THE EXHAUST DUCT FROM THE |
| OUTLET OF THE GENERATOR TO THE TERMINATION CAP ON THE |
| ROOF- INDICATE THE TYPE OF DUCT WORK AND HOW THE DUCT |
| WILL BE GUARDED WHERE IT PENETRATES THE COMBUSTIBLE |
| ROOF PLYWOOD- REFER TO SECTION 8.3.3 NFPA-37. |
| 7) PROVIDE A SEQUENCE OF OPERATION FOR THE |
| THERMOSTATICALLY CONTROLLED EXHAUST FAN- SEE SHEET |
| M101. |
| 8) REFER TO SECTION 501.3.1 ITEM #1 AND VERIFY |
| COMPLIANCE FOR THE GENERATOR EXHAUST TERMINATION. |
| 9) PLEASE ADJUST THE VALUE ON THE PERMIT APPLICATION TO |
| INCLUDE THE COST OF THE PROJECT BASED ON LABOR, |
| MATERIALS, EQUIPMENT, DESIGN FEES, OVERHEAD AND PROFIT |
| ETC.- REFER TO SECTION 109.3 WPB AMENDMENTS TO THE |
| FBC-14. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |
| |