2015-11-19 06:40:381) SHOW THE EHD NUMBER OF CORRUGATED STAINLESS STEEL
 TUBING FOR EACH PIPE SIZE IF BEING USED. WPB AMENDMENTS
 TO FBC SEC. 107.2.1.
 2) SUBMIT CALCULATIONS FOR COMBUSTION AIR PER THE
 FBC-2014 FUEL GAS CODE SEC. 304.
 3) SUBMIT A DETAIL SHOWING THE TYPE, LOCATION, SIZE AND
 TERMINATION OF THE GAS VENTS PER FBC-2014 FUEL GAS CODE
 SEC. 502 THRU 505.
 4) SUBMIT MANUFACTURER?S SPECIFICATION SHEETS FOR ALL
 GAS EQUIPMENT TO VERIFY COMPLIANCE WITH STANDARDS NFPA
 54, NFPA 58, AND FBC-2014 FUEL GAS SEC. 402.2, AND
 301.3. GAS APPLIANCES SHALL BE LISTED AND LABELED PER
 SEC.301.3 OF 2014 FUEL GAS CODE
 5) THE 1/2 " GALVANIZED DROP TO THE SUMMER KITCHEN
 SHALL BE 3/4". TABLE 402.4(2) FGC.
 6) THE 1/2" CSST TO THE SUMMER KITCHEN SHALL BE 3/4".
 TABLE 402.4(15) FGC.
 7) THE 3/4" CSST DOWNSTREAM OF THE 1" GALVANIZED SHALL
 BE 1". TABLE 402.4(15) FGC.
 8) THE PE TO THE POOL HEATER SHALL BE 1 1/2 ". TABLE
 402.4 (21) FGC.
 9) THE PLANS REFER TO TABLE 402.4 (2) FOR PE PIPE. THIS
 TABLE IS FOR SCH. 40 METALLIC PIPE. INDICATE THE
 CORRECT SIZING TABLES FOR ALL THE DIFFERENT TYPE OF
 PIPE MATERIAL ON THE PLANS.
 10) IF ANY MP REGULATORS ARE GOING TO BE INSTALLED,
 SHOW THE LOCATION ON THE PLANS AND LIST THE CORRECT
 SIZING TABLE FOR THE SYSTEM.
 11) THE BTU LOAD OF THE APPLIANCES LISTED ON THE GAS
 TABLE DOES NOT CORRELATE WITH THE BTU LOAD SHOWN ON THE
 GAS RISER. CLARIFY.
  
  
 PLUMBING PLAN REVIEW
 TIM LARGE
 CHIEF PLUMBING INSPECTOR
 561-805-6692
 [email protected]


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved