2015-11-05 09:37:51 | 1ST REVIEW: FBC 2014 MECHANICAL |
| PERMIT #15110034 |
| 11/5/2015 |
| |
| 1) PROVIDE AN AIR VELOCITY CALCULATION FOR THE NEW |
| GREASE DUCT- SECTION 506.3.4. |
| 2) SHOW COMPLIANCE WITH SECTION 508.1.1 MAKEUP AIR |
| TEMPERATURE. |
| THE TEMPERATURE DIFFERENTIAL BETWEEN MAKEUP AIR AND THE |
| AIR IN THE CONDITIONED SPACE SHALL NOT EXCEED 10?F |
| (6?C) EXCEPT WHERE THE ADDED HEATING AND COOLING LOADS |
| OF THE MAKEUP AIR DO NOT EXCEED THE CAPACITY OF THE |
| HVAC SYSTEM. |
| 3) SHOW COMPLIANCE WITH SECTION 507.9 CLEARANCES FOR |
| TYPE I HOOD. |
| A TYPE I HOOD SHALL BE INSTALLED WITH A CLEARANCE TO |
| COMBUSTIBLES OF NOT LESS THAN 18 INCHES (457 MM). |
| EXCEPTION: CLEARANCE SHALL NOT BE REQUIRED FROM GYPSUM |
| WALLBOARD OR 1/2-INCH (12.7 MM) OR THICKER CEMENTITIOUS |
| WALLBOARD ATTACHED TO NONCOMBUSTIBLE STRUCTURES |
| PROVIDED THAT A SMOOTH, CLEANABLE, NONABSORBENT AND |
| NONCOMBUSTIBLE MATERIAL IS INSTALLED BETWEEN THE HOOD |
| AND THE GYPSUM OR CEMENTITIOUS WALLBOARD OVER AN AREA |
| EXTENDING NOT LESS THAN 18 INCHES (457 MM) IN ALL |
| DIRECTIONS FROM THE HOOD. |
| 4) PROVIDE A SUBMITTAL FOR THE DUCT WRAP WITH A REVIEW |
| AND APPROVAL STAMP FROM THE DESIGN PROFESSIONAL OF |
| RECORD. |
| 5) SHEET 5: PROVIDE THE CLEARANCE DISTANCE MEASURES |
| FROM THE GREASE DUCT TERMINATION CAP TO ADJACENT |
| BUILDINGS, ADJACENT PROPERTY LINES, AND PARTS OF THE |
| SAME OR CONTIGUOUS BUILDING- SECTION 506.3.13.3 |
| 6) SITE SPECIFIC WIND LOAD ENGINEERING IS REQUIRED FOR |
| TIE DOWN OF THE NEW ROOFTOP EXHAUST AND SUPPLY FANS AND |
| CURB ADAPTERS- SECTION 301.15. THE ENGINEER OF RECORD |
| SHALL PROVIDE WIND DESIGN CRITERIA, DESIGN PRESSURES, |
| AND COMPLETE DETAILS FOR INSTALLATION, INCLUDING |
| REVIEWED AND APPROVED SUBMITTALS FOR THE CURB ADAPTERS, |
| AND REVIEWED AND APPROVED NOA'S FOR THE FANS. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |