Plan Review Notes For Permit 15101016 |
Permit Number |
15101016 |
|
Review Stop |
G |
Sequence Number |
2 |
|
Notes |
Date |
Text |
2015-12-21 06:29:41 | 1) THE GAS SHALL BE DONE UNDER A SEPARATE PERMIT.A | | SEPARATE PERMIT APPLICATION SHALL BE SUBMITTED FOR THE | | GAS INSTALLATION. | | 2) SUBMIT A GAS RISER DIAGRAM FOR REVIEW. SHOW THE | | DISTANCE FROM THE METER TO THE MOST REMOTE OUTLET, THE | | TYPE OF PIPE, THE PSI OF THE SYSTEM, AND INCLUDE ALL | | EXISTING GAS APPLIANCES AND THE RESPECTIVE BTU LOADS OF | | EACH APPLIANCE TO ENSURE PROPER SIZING.WPB AMEND. TO | | FBC SEC.107.3.5.3. | | 3) SUBMIT COMBUSTION AIR CALCULATIONS FOR THE DRYER. | | FGC 304. | | | | GAS WILL BE UNDER A SEPARATE PERMIT. TKL.. | | | | | | PLUMBING PLAN REVIEW | | TIM LARGE | | CHIEF PLUMBING INSPECTOR | | 561-805-6692 | | [email protected] | | |
|