2015-09-05 08:43:17 | 1) SHT.1.0 (A) - THE ACCESSIBILITIY FIGURES ARE FROM A |
| PREVIOUS CODE EDITION. SUBMIT THE CORRECT FIGURES FROM |
| THE 2014 FBC-ACCESSIBILITY. |
| 2) THE OCCUPANT LOAD IS SHOWN AS 156 PERSONS. THE |
| NUMBER OF WATER CLOSETS IS DEFICIENT FOR THE OCCUPANT |
| LOAD. COMPLY WITH 2014 FBC-PLUMBING TABLE 403.1. |
| 3) SHT.1.1 (A). SHOW THE BTU LOAD FOR EACH GAS |
| APPLIANCE ON THE EQUIPMENT SCHEDULE.WPB AMEND. TO FBC |
| SEC. 107.2.1. |
| 4) SHT.3.1P - THE GAS TABLE REFERENCED IS FOR UNDILUTED |
| PROPANE @10 PSI BUT THE PLAN NOTES 11 INCH WATER COLUMN |
| WITH A .5 PRESSURE DROP SYSTEM. CLARIFY. |
| 5) A THOROUGH REVIEW OF THE GAS SYSTEM CANNOT BE DONE |
| UNTIL THE THE CORRECT SIZING TABLE IS SUBMITTED. |
| 6) THE GAS LOAD CALC TABLE LISTS AN 1 1/2 INCH GAS LINE |
| TO THE HOT PLATE AND THIS LINE IS FED BY A 1 INCH LINE? |
| THIS DOES NOT MAKE SENSE. CLARIFY. |
| 7) SIZE ALL PIPE SECTION OF THE GAS RISER. WPB AMEND. |
| TO FBC SEC. 107.2.1. THE ENTIRE SYSTEM SHALL BE SIZED |
| USING THE 150 FEET COLUMN. |
| 8) THE HOT PLATE IS NOT SHOWN ON THE GAS RISER. |
| CLARIFY. |
| 9) WHAT IS THE NUMBER "2138K ON THE GAS DRAWING? |
| 10) SHT. 3.1P NOTES THE GAS IS SIZED PER 2010 FUEL GAS |
| CODE. IF THIS IS NEW PIPING, IT SHALL BE SIZED PER THE |
| 2014 FUEL GAS CODE. |
| 11) THE WATER CLOSET IN THE MEN'S RESTROOM IS MISSING |
| FROM THE SANITARY RISER. |
| 12) THE SANITARY VENT FOR THE TOILET ROOMS GOES |
| NOWHERE. CLARIFY. |
| 13) SHOW CONTINUATION POINT OF THE SANITARY VENT FOR |
| THE MOP SINK. |
| 14) SUBMIT DETAILS FOR THE VENT FOR THE TANKLESS WATER |
| HEATER. |
| 15) THE LAYOUT OF THE DRAIN FOR THE ICE BIN/ICE MAKER |
| ON THE PLAN VIEW DOES NOT MATCH THE RISER DIAGRAM. |
| CLARIFY. |
| 16) IF THE WASTE FROM THE ICE MAKER/ICE BIN IS CLEAR |
| WATER WASTE, IT SHALL NOT BE DISCHARGED TO THE GREASY |
| WASTE AS SHOWN. CLARIFY.2014 FPC SEC. 1003..2. |
| 17) SHT. 3.1P - SHOWS A RINSE FAUCET LABELED AS GW |
| DISCHARGING TO THE SANITARY. CLARIFY.MY CALCULATIONS |
| FOR THE GREASE INTERCEPTOR ARE 1856 NOT 1956. CORRECT |
| THE CALCULATIONS ON THE PLANS. |
| 18) SHT. 3.1P - SHOWS THE SANITARY DISCHARGING TO THE |
| GREASE INTERCEPTOR AND THE GREASY WASTE TO NOWHERE. |
| CLARIFY. |
| 19) SHOW THE SIZE AND LOCATION OF THE LP TANK. INDICATE |
| IF IT IS NEW OR EXISTING, ABOVE GROUND OR UNDERGROUND, |
| NEAR A TRAFFIC AREA OR WHERE TRAFFIC COULD BE EXPECTED, |
| ETC. |
| 20) SHOW THE DISTANCE OF THE LP TANK FROM THE |
| STRUCTURE. |
| 21) SUBMIT WIND LOAD ENGINEERING FOR THE TANK IF IT IS |
| ABOVEGROUND. 2014 FGC SEC.301.10. |
| 22) SUBMIT A WATER RISER DIAGRAM FOR REVIEW. WPB AMEND. |
| TO FBC SEC. 107.3.5.1.3. |
| |
| PLUMBING PLAN REVIEW |
| TIM LARGE |
| CHIEF PLUMBING INSPECTOR |
| 561-805-6692 |
| [email protected] |
| |
| |
| |
| |
| |