2015-08-12 10:58:05 | 1ST REVIEW: FBC 2014 MECHANICAL |
| PERMIT #15080353 |
| 8/12/15 |
| |
| 1) REFERENCE SECTION C403.2.1 FBC-14 ENERGY |
| CONSERVATION: PROVIDE COOLING AND HEATING LOAD |
| CALCULATIONS FOR THE NEW AC SYSTEMS IN ACCORDANCE WITH |
| ACCA MANUAL N OR THE ACCA/ASHRAE STANDARD 183. THE |
| SUBMITTED RHEEM DESIGN STAR LOAD CALCULATION IS NOT AN |
| ACCA APPROVED CALCULATION METHOD. |
| 2) REFERENCE SECTION C101.4.5 FBC-14 ENERGY |
| CONSERVATION: "ANY NONCONDITIONED SPACE THAT IS ALTERED |
| TO BECOME CONDITIONED SPACE SHALL BE REQUIRED TO BE |
| BROUGHT INTO FULL COMPLIANCE WITH THIS CODE". THE PLAN |
| INDICATES NEW AC IN THE STORAGE ROOM WHICH PREVIOUSLY |
| HAD NO AC SYSTEM. PLEASE REVIEW CHAPTER 4 FOR |
| COMPLIANCE REQUIREMENTS, AND SUBMIT ENERGY CALCULATIONS |
| USING FLORIDA BUILDING COMMISION SOFTWARE AS NOTED IN |
| SECTION C101.5.1. PLEASE NOTE THAT MODIFICATIONS TO THE |
| BUILDING FOR IMPROVED ENERGY PERFORMANCE MAY BE |
| REQUIRED. |
| 3) THE AIR CONDITIONING SYSTEM GENERAL NOTES, AND THE |
| AHU INSTALLATION DETAIL NOTES HAVE PRINT THAT IS TOO |
| FAINT TO READ. PLEASE ENLARGE AND DARKEN THE PRINT TO |
| EXPEDITIE THE REVIEW- WPB AMENDMENTS TO SECTION 107.2 |
| FBC-14 BUILDING CODE. |
| 4) INDICATE CLEARLY HOW AIR IS BEING RETURNED TO THE |
| AHU. THE AHU DETAIL HAS A NOTE INDICATING A RETURN DUCT |
| ATTACHED TO A RETURN PLENUM BOX UNDER THE UNIT, BUT THE |
| PLAN IS NOT INDICATING RETURN DUCTWORK. IS THERE A |
| RETURN GRILL IN THE PLENUM BOX? IF SO, PLEASE INDICATE |
| THE DIMENSIONS. |
| 5) THE PLAN INDICATES A "SMOKE DETECTOR" AT THE AIR |
| HANDLER: PLEASE CLARIFY THE CONTROL OPERATION OF THE |
| DEVICE PERTAINING TO THE NEW AND EXISITNG AC SYSTEMS- |
| REFER TO SECTION 606.4 AND 606.4.1 FBC-14 MECHANICAL. |
| 6) PROVIDE VENTILATION CALCULATIONS FOR THE NEW |
| CONDITIONED SPACE IN COMPLIANCE WITH TABLE 403.3. |
| INDICATE ON THE PLAN THE REQUIRED AND PROVIDED CFM'S OF |
| O/A AIR. |
| 7) REFER TO SECTION C403.2.4.4 FBC-14 ENERGY |
| CONSERVATION AND INDICATE COMPLIANCE WITH SHUTOFF |
| DAMPER CONTROLS FOR THE O/A INTAKE. |
| 8) CORRECT THE NOTE INDICATING 26 GAUGE HANGING STRAPS |
| FOR THE FIBERGLASS DUCT WORK- 22 GAUGE IS REQUIRED PER |
| FIGUTRE 6-1 SMACNA- FIBROUS GLASS DUCT CONSTRUCTION |
| STANDARDS- 2010. |
| 9) SUBMIT AN ELECTRICAL PLAN AND AN ELECTRICAL |
| SUB-PERMIT FOR REVIEW; OR INDICATE ON THE PLAN THAT THE |
| ELECTRICAL WILL BE DONE UNDER A SEPARATE PRIMARY |
| PERMIT. |
| |
| CHRISTOPHER L. COLE |
| MECHANICAL PLANS EXAMINER |
| 561-805-6719 |
| [email protected] |
| |
| |
| |